HI BUILD LIMITED (formerly HOME BUILDERS BOP LTD) v FORMAN [2018] NZHC 1320
The trustees' claim was properly characterised as a breach of contract; the six-year limitation under s 4(1)(a) Limitation Act 1950 applies; the cause of action accrued when the contractual breaches crystallised upon the end of the contract and failure to perform the agreed 'wash up' reconciliation (when HBL ceased...
Source-derived case information.
- Citation
- [2018] NZHC 1320
- Parties
- Appellant: HI BUILD LIMITED (formerly HOMEBUILDERS BOP LTD); Respondent: NIGEL KELVIN FORMAN and CLARELESLEY TURNER as trustees of the NK Forman Family Trust
- Court
- High Court
- Jurisdiction
- New Zealand
- Judgment Date
- 6 June 2018
- Procedural Posture
- Appeal Against Arbitral Award / Final Judgment on Appeal
- Outcome
- Appeal dismissed
- Legal Topics
- Payment Claims, Overcharging, Accrual of Cause of Action, Limitation Period, Money Had and Received, Wash Up Reconciliation
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
HI BUILD LIMITED (formerly HOMEBUILDERS BOP LTD)
Appellant
NIGEL KELVIN FORMAN and CLARELESLEY TURNER as trustees of the NK Forman Family Trust
Respondent
Procedural Posture
Appeal Against Arbitral Award / Final Judgment on Appeal
Legal Issues
- 1 Whether the trustees' claim was for breach of contract or money had and received
- 2 Which limitation period applied to the claim
- 3 When the cause of action accrued for limitation purposes
Ratio Decidendi
The trustees' claim was properly characterised as a breach of contract; the six-year limitation under s 4(1)(a) Limitation Act 1950 applies; the cause of action accrued when the contractual breaches crystallised upon the end of the contract and failure to perform the agreed 'wash up' reconciliation (when HBL ceased work in December 2010); therefore the trustees' claims were brought within the six-year limitation period and the appeal was dismissed.
Court Disposition
Appeal dismissed
Orders
- Appeal dismissed
- Quantum to be determined in accordance with the arbitrator's award; if parties cannot agree they are to return to the arbitrator
Full Case Text
Judgment text and source record
1 paragraphs
HI BUILD LIMITED (formerly HOME BUILDERS BOP LTD) v FORMAN [2018] NZHC 1320 [6 June 2018]IN THE HIGH COURT OF NEW ZEALANDTAURANGA REGISTRYI TE KŌTI MATUA O AOTEAROATAURANGA MOANA ROHECIV-2017-470-000183[2018] NZHC 1320UNDER The Arbitration Act 1996IN THE MATTER of an appeal against an arbitral awardBETWEEN HI BUILD LIMITED (formerly HOMEBUILDERS BOP LTD)AppellantAND NIGEL KELVIN FORMAN and CLARELESLEY TURNER as trustees of the NKForman Family TrustRespondentsHearing: 9 April 2018Appearances: T Conder for the AppellantJ Delaney for the RespondentsJudgment: 6 June 2018JUDGMENT OF WOOLFORD JThis judgment was delivered by me on Wednesday, 6 June 2018 at 4:00 pmpursuant to r 11.5 of the High Court Rules.Registrar/Deputy RegistrarSolicitors: Holland Beckett Law, TaurangaHarris Tate, TaurangaCounsel: J Delaney, TaurangaIntroduction[1] The appellant, Hi Build Limited ("HBL"), and the respondents, Nigel Formanand Clare Turner as trustees of the NK Forman Family Trust ("the trustees"), submitteda dispute to arbitration. Essentially, the trustees said they were overcharged by HBLin relation to construction work undertaken by HBL. The arbitrator largely found forthe trustees, leaving quantum to be determined between the parties.[2] On 31 October 2017, Brewer J granted HBL leave to appeal the arbitrator'saward on a single question: did the arbitrator err in concluding that claims in relationto payment claims 1 to 9 were brought within time?1 The term "payment claim" isdefined in the Construction Act 2002. I use that term and invoice interchangeably.HBL argues on appeal, as it did in the arbitration, that the trustees' claim in relation topayment claims 1 to 9 was not brought in time.[3] The question on appeal gives rise to four interrelated issues. First, should thetrustees' claim in the arbitration be characterised as being for breach of contract ormoney had and received? Second, what limitation period applies to the claim? Third,when did time begin to run? Fourth, was the trustees' claim brought in time? Thisjudgment determines these issues, and accordingly, the appeal.Facts[4] HBL completed construction work for the trustees between April 2009 andDecember 2010 pursuant to a written construction contract. The work consisted ofrenovating trust property, namely a house in Tauranga.[5] The contract provided that payment for the work was to occur on a "charge-upbasis". Specifically, the key contractual terms regarding payment were:(a) The final contract price would be "as expended" – the total amount ofall invoiced claims.1 Home Builder BOP Ltd v Forman [2017] NZHC 2155.(b) The hourly charge-out rate for work [interpreted to be work undertakendirectly by HBL's director, Stuart Wood] would be $38.00 per hourexcluding GST.(c) The rate for travel would be $0.60 per kilometre and $38.00 per hour,both excluding GST, for Stuart Wood only.(d) Materials, builders' labour and subtrades would be charged at cost plus9 per cent, including GST. The arbitrator found that the exact GSTtreatment would depend on how HBL was charged. Further, HBLwould pass on any trade discounts to the trustees. HBL would also, onrequest, make copies of trade suppliers' and subcontractors' invoicesavailable to the trustees.(e) HBL would invoice the trustees monthly. All payments were duewithin seven working days. HBL was entitled to suspend work, afterfollowing proper procedure, where the trustees failed to pay anyinvoiced amount in full by the date due for the payment.[6] Over the course of its work, HBL invoiced the trustees for $917,522.25 in total,across 21 payment claims, of which the trustees paid $887,783.29.[7] Mr Forman raised concerns about overcharging throughout the work. He saysthat HBL told him, in response, to keep track of any credit claims because they couldresolve it later.[8] The parties' relationship eventually broke down. HBL ceased work inDecember 2010. After some correspondence in early 2011, there was then no contactbetween the parties for some years. In 2015, the trustees raised concerns regardingovercharging/overpayments. A series of discussions followed.[9] By letter dated 17 December 2015, HBL advised the trustees it intended tocommence summary judgment proceedings if payment in the amount of $94,476.48,which included interest, was not made by 11 January 2016. This related to unpaidinvoices.[10] On or about 18 December 2015, the trustees commenced proceedings againstHBL for breach of contract in the District Court. The trustees advised HBL of its claimon that date but not that it had filed proceedings, apparently to not "de-rail mediationdiscussions".[11] A mediation meeting was held on 4 February 2016. The matter was not settled.[12] HBL, by letter dated 9 February 2016, told the trustees that it considered theDistrict Court did not have jurisdiction in this matter because of the arbitration clause.Clearly, at this point HBL had become aware of the District Court proceedings. Thearbitration clause in the contract provides:75 Subject to clause 74, either party may, by written notice to the otherparty, ask that the dispute be referred to arbitration. Such notice shallspecify the matter or matters at issue and give detailed particulars ofthe Dispute. If both agree then the Arbitration shall be by a singlearbitrator and in accordance with the Arbitration Act 1996.[13] The trustees gave notice of their intention to arbitrate by email on 9 February2016. HBL, on 11 February 2016, agreed to arbitration, while maintaining its positionthat the trustees' claim as far as it related to payment claims 1 to 9 was out of time.[14] Around March 2016, HBL applied for summary judgment in the District Courtin relation to unpaid invoices. These documents were served on the trustees on19 May 2016. The trustees then, in response, served their statement of claim forbreach of contract on HBL on 20 May 2016.[15] The District Court proceedings were then stayed, by consent, pendingarbitration.Arbitration[16] The parties appointed Derek Firth MNZM as the sole arbitrator on or about1 November 2016. Mr Firth is a barrister and experienced arbitrator, with particularexperience in construction disputes.[17] In arbitration, the trustees pursued their claim that HBL overcharged. Theyclaimed HBL overcharged them by $133,477.69 and that they overpaid $103,745.73.HBL counterclaimed it was owed $34,739.84 in unpaid invoices. Eventually, theamount claimed by the trustees was reduced to $97,609.57, and the counterclaim to$29,212.69.[18] The dates of payment claims 1 to 9, as per the invoices, are:Payment Claim Date1 4 June 20092 15 July 20093 5 August 20093B 25 August 20094 15 September 20095 21 October 20096 11 November 20097 11 December 20098 11 January 20109 3 February 2010[19] Some further details about the trustees' claim are necessary. They claimed, inessence, that they were overcharged in the following ways:(a) The invoices contained errors and inaccuracies. As a result of the errorsand inaccuracies, the trustees were overcharged $46,924.99.(b) The trustees were charged for builders' labour at a rate of $38.00 perhour plus 9 per cent plus GST where they should have been charged atcost plus 9 per cent, with GST treatment depending on the way HBLwas billed. On this basis, the trustees claimed they were overchargedby $87,710.94.(c) The trustees were charged for Stuart Wood's labour at a rate of $38.00per hour plus 9 per cent plus GST, where they should have been chargedat $38.00 per hour plus GST.[20] HBL maintained throughout the arbitration that it was entitled to charge thetrustees as it did. At most, it considered it overcharged the trustees by around $500.00.[21] Mr Firth made an interim award on 10 May 2017. While he did not expresslyaddress the basis of the claim or when the contract was breached, his key findings canbe summarised in four points. First, all of Stuart Wood's time (whether for workingor travelling) was to be charged at a fixed rate of $38.00 per hour plus GST but it didnot attract the nine per cent margin. Second, the cost of builders' labour was to becharged at actual cost plus nine per cent, with GST treatment depending on how HBLwas charged. Third, the trustees were entitled to see reasonable proof of what waspaid and the basis on which it was calculated. The trustees did not have to pay for anywork not supported by an invoice. Fourth, the trustees were entitled to the benefit ofall credits received by HBL.[22] Mr Firth further determined that HBL was entitled to the amount it claimedwas unpaid, subject to the extent that the trustees' claim succeeded.[23] As regards the limitation issue, the arbitrator held that time did not begin to runin relation to any payment claim until HBL ceased work. It followed that the trustees'entire claim was brought in time. Mr Firth said:I am well aware of the principles relating to the time when a cause of actionaccrues and the identification of that time from when all relevant material isavailable, but that is not an argument I have ever heard having been applied toperiodic payments during a construction contract. Many constructioncontracts last for many years and it has been accepted around the world indomestic and international arbitrations that limitation periods do notcommence to run until the end of the contract.Otherwise there would be havoc on large projects outlasting the limitationperiod.Accordingly, all the claims are within time.Issue one: are the claims in contract or money had and received?[24] The trustees' claim was either for breach of contract or for money had andreceived. The arbitrator did not expressly address the basis of the claim. It is necessaryto determine it now because the legal basis of the claim potentially impacts whichlimitation period applies and when time started to run.[25] Brewer J, in his leave judgment, proceeded on the basis the claim was formoney had and received as he considered "an overpayment of a contract is not a breachof contract".2 However, I note Brewer J specifically said he had not seen the way inwhich the case was put before the arbitrator. Counsel for the trustees also advise thatthe nature of the cause of action was not addressed by HBL and it was not discussedin the hearing before Brewer J.[26] HBL has now adopted Brewer J's approach. It says where a claimantvoluntarily paid money to a defendant but would not have done so absent a mistake offact made by the claimant, the claim must be in money had and received.[27] The trustees, on the other hand, claim HBL breached the contract byovercharging them. And that the arbitrator upheld this claim.[28] I consider the trustees' claim was for breach of contract for three reasons. First,the facts support a claim for breach of contract. A failure to perform a contractualobligation amounts to a breach of contract. I adopt following statement from thelearned authors of Treitel – The Law of Contract:3A breach of contract is committed when a party without lawful excuse fails orrefuses to perform what is due from him under the contract, or performsdefectively or incapacitates himself from performing.[29] In the present case, HBL was under a contractual obligation to charge andinvoice the trustees in accordance with the terms outlined above at [5].2 Home Builder BOP Ltd v Forman [2017] NZHC 2155.3 Edwin Peel (ed) Treitel — The Law of Contract (14th ed, Sweet & Maxwell, London, 2015) at[17-049].[30] While it was not contained in the written contract, I am also satisfied that theparties agreed, subsequent to the written contract, to conduct a "wash up" exercise toresolve any overcharging or invoicing errors at the end of the contract. That agreementformed part of the contract between the parties. I am satisfied by Mr Forman'sevidence:(a) He explains that when he raised issues about overcharging with HBL,which he did almost every month, he was told to keep track of creditclaims because they could be "sorted" later. Mr Forman states that hehad "agreed with Stuart that [they] would do a final wash up at the endof the bill" and that when he raised issues with HBL "Stuart wouldpromise to look into credits and deal with them in future".(b) Mr Wood does not accept they agreed to engage in a wash up exercisebut Mr Forman refers to an email dated 2 November 2010 in whichMr Wood mentioned dealing "at one time with credits due, invoicingerrors and short payments".(c) Accordingly, Mr Forman kept a record of the overcharges "in the beliefthat these would be reconciled at a later date".(d) On occasion – for example in relation to payment claim 3 – Mr Formanraised issues with HBL and invoices were adjusted and reissued.(e) Mr Forman ceased making payments near the end of the contractbecause he considered that by that stage he was substantially in creditand that this would be accounted for in the wash up exercise.(f) Mr Forman gave HBL a summary of his credit claims in December2010 in an attempt to complete the wash up exercise.(g) HBL wrote to Mr Forman on 19 February 2011. Clearly, it did notconsider that significant overcharging had occurred. It stated theaccount was approximately $40,000.00 in arrears. However,significantly, HBL acknowledged there were "some credits to approveand some minor invoice items to check". Aside from this, HBL did notspecifically address the credit claims Mr Forman had sent.(h) Mr Forman followed up twice in March 2011. HBL did not respond.[31] This was not a case of simple overpayment. The trustees overpaid becauseHBL overcharged them. This case is therefore, in my view, best characterised as oneof breach of contract through overcharging. But that overcharging was not crystalliseduntil the parties failed to conduct the wash up exercise at the end of the contract.[32] Second, the claim was specifically pleaded as being for a breach of contractbefore the arbitrator. For example, the statement of claim says:As a consequence of the above breaches of the contract, the claimant wassubstantially overcharged for the works and seeks recovery of theoverpayment.The respondent charged more than he was contractually entitled to do, so theclaimant is entitled to recover the overcharges as a breach of contract.The respondent failed to seek enforcement of its statutory right under theConstruction Contracts Act regime for Payment Claims 1-10. However, thisdoes not mean that the claimant's action for breach of contract is similarlylimited.[33] Third, while the trustees might have been able to make out a claim for moneyhad and received, in my view, that does not mean they could not claim for breach ofcontract. They simply had an alternative claim for money had and received, as wasthe case in Air New Zealand Ltd v Newfoundworld Site 2 (Hotel) Ltd.4 I am notsatisfied that they pursued such an alternative claim.4 Air New Zealand Ltd v Newfoundworld Site 2 (Hotel) Ltd [2017] NZHC 1131 at [84].Issue two: what limitation period applies to the claims?[34] The parties agree that the six year limitation period under s 4(1)(a) of theLimitation Act 1950 applies, regardless of the nature of the claim. That sub-sectionapplies to "actions founded on simple contract or on tort".[35] There appears to be some debate as to whether a claim for money had andreceived is an action founded on "simple contract". Given my conclusion on the firstissue, it is unnecessary to engage in that debate. The six year limitation period ins 4(1)(a) applies.Issue three: when did time begin to run?[36] Next, I need to determine when time began to run. On the trustees' case, timebegan to run either when the contract was concluded or when there was a "netoverpayment". Either results in the claims being brought in time.[37] On the other hand, HBL says each claim for overpayment accrued on the dayoverpayment was made. On this approach, the trustees' claim as regards paymentclaims 1 to 9 was not brought in time and is accordingly time-barred.[38] Time begins to run when a cause of action accrues. A cause of action accrueswhen every fact exists which the plaintiff would need to prove to establish its case.5Halsbury's Laws of England explains:6Apart from any special provision, a cause of action normally accrues whenthere is in existence a person who can sue and another who can be sued, andwhen there are present all the facts which are material to be proved to entitlethe claimant to succeed.5 Williams v Attorney-General [1990] 1 NZLR 646 (CA) at 678.6 Halsbury's Laws of England (5th ed, 2016) vol 68 Limitation Periods at [920].[39] In a case for breach of contract, the cause of action is complete upon breach,without the need for actual loss or damage.7 Keating on Construction Contracts8 andKennedy-Grant and Weatherall on Construction Law confirm this principle.9[40] In my view, the contract in the present case was breached when theovercharging and inaccurate invoicing was not corrected through a wash up exercise.That exercise should have been conducted when HBL ceased work, or within areasonable period from that time. It was not. As a result, the breaches crystallised inDecember 2010 at the earliest. I do not consider it was, objectively, the parties'intention that the contract should have been regarded as breached through invoicingerrors before that time.Issue four: were the claims brought in time?[41] As explained above, the earliest date at which the contract was breached wasDecember 2010 when HBL ceased work. The trustees had six years from that date tobring their claim.[42] There is disagreement between the parties as to when time ceased to run. HBLsays time ran until the trustees gave notice of their intention to arbitrate on 9 February2016. The trustees, on the other hand, say that time stopped running on 18 December2015 when they filed a claim in the District Court.[43] This disagreement is immaterial given the conclusions I have reached on issuesone to three. Both dates contended for were within six years from the earliest breachdate, when HBL ceased work in December 2010. All the claims were brought in time.Conclusion[44] The appeal is dismissed.7 Invercargill City Council v Hamlin [1994] 3 NZLR 513 (CA) at 536 and Gedye v South [2010]NZCA 207, [2010] 3 NZLR 271 at [44].8 Stephen Furst and Vivian Ramsey Keating on Construction Contracts (10th ed, Sweet & Maxwell,London, 2016) at [16-025].9 Tómas Kennedy-Grant and Michael Weatherall Kennedy-Grant and Weatherall on ConstructionLaw: The Underlying Law — Contract, Torts and Legislation (LexisNexis, Wellington, 2017) at[55,360].[45] It is now for the parties to determine quantum in accordance with Mr Firth'saward. If they are unable to do so, they should return to Mr Firth in accordance withthe procedure outlined on page 8 of his interim award.[46] I see no reason to depart from the fundamental principle that costs shouldfollow the event. My assessment is that 2B costs are appropriate. If the parties cannotagree, I will receive memoranda of no more than three pages by 30 June 2018following which I will make a decision on the papers._________________________Woolford J