KIWI PROPERTY HOLDINGS LTD v FLETCHER CONSTRUCTION COMPANY LTD [2018] NZHC 1745

KIWI PROPERTY HOLDINGS LTD v FLETCHER CONSTRUCTION COMPANY LTD [2018] NZHC 1745

Leave to appeal was refused because the proposed appeal raised fact‑heavy or mixed questions tied to the arbitrator's primary factual findings about foreseeability of encountered steel; those findings are unlikely to be disturbed on a legal question appeal and therefore the challenge did not raise an arguable...

Source-derived case information.

Citation
[2018] NZHC 1745
Parties
Applicant: Kiwi Property Holdings Limited; Respondent: Fletcher Construction Company Limited
Court
High Court
Jurisdiction
New Zealand
Judgment Date
17 July 2018
Procedural Posture
Application for Permission to Appeal Arbitral Award Under the Arbitration Act 1996 / Leave Application (dismissed)
Outcome
Application for permission to appeal dismissed
Legal Topics
Permission to Appeal, Variation Clause (clauses 9.5.2 and 9.5.4), Foreseeability, Contractual Interpretation, Review of Arbitral Findings
Arbitration Contract Construction Law Civil Procedure Permission to Appeal Variation Clause (clauses 9.5.2 and 9.5.4) Foreseeability Contractual Interpretation +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 4 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Kiwi Property Holdings Limited

Applicant

Fletcher Construction Company Limited

Respondent

Procedural Posture

Application for Permission to Appeal Arbitral Award Under the Arbitration Act 1996 / Leave Application (dismissed)

  1. 1 Whether the arbitrator misapplied contract clauses 9.5.2 and 9.5.4 (variation for unforeseen physical conditions)
  2. 2 Whether strikes of existing steel were reasonably foreseeable when Fletchers tendered
  3. 3 Whether the proposed appeal raises a question of law sufficient to grant leave

Ratio Decidendi

Leave to appeal was refused because the proposed appeal raised fact‑heavy or mixed questions tied to the arbitrator's primary factual findings about foreseeability of encountered steel; those findings are unlikely to be disturbed on a legal question appeal and therefore the challenge did not raise an arguable question of law warranting leave.

Court Disposition

Application for permission to appeal dismissed

Orders

  • Kiwi's application for permission to appeal is dismissed
  • Costs to be agreed; if agreement cannot be reached the parties are to file and serve memoranda of no more than four pages: Kiwi by 5 pm Tuesday 31 July 2018 and Fletchers by 5 pm Tuesday 7 August 2018