SINGH AND AND BOUCHIER v POTTERS PARK PROPERTY LTD [2014] NZHC 2392

SINGH AND AND BOUCHIER v POTTERS PARK PROPERTY LTD [2014] NZHC 2392

Clause 3 of the agreement are conditions precedent; there is no necessary implication that Potters was obliged on execution to apply to Council or notify for a two-way right-of-way for the Trust; Potters did not breach the agreement and its obligations ended when the Trust failed to obtain the consents within the...

Source-derived case information.

Citation
[2014] NZHC 2392
Parties
Plaintiff: Mahendra Singh; Plaintiff: Geoffrey Hugh Bouchier; Defendant: Potters Park Property Limited
Court
High Court
Jurisdiction
New Zealand
Judgment Date
1 October 2014
Procedural Posture
Civil (contract/property/resource Management) / Final Judgment (high Court)
Outcome
Judgment for defendant; plaintiff's claims for specific performance and damages dismissed; counterclaim succeeds
Legal Topics
Easement, Right of Way, Specific Performance, Conditions Precedent, Implied Contractual Obligation, Waiver, Damages, Caveat, Trespass
Contract Property Law Equity Resource Management Easement Right of Way Specific Performance Conditions Precedent +5 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 5 Authorities cited 7 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Mahendra Singh

Plaintiff

Geoffrey Hugh Bouchier

Plaintiff

Potters Park Property Limited

Defendant

Procedural Posture

Civil (contract/property/resource Management) / Final Judgment (high Court)

  1. 1 Whether Potters was obliged on execution to apply to Council or disclose the agreement to secure two-way traffic for the Trust's right-of-way
  2. 2 Whether condition 3(d) could be waived later by the Trust
  3. 3 Whether Potters' obligation to consent continued after the Trust abandoned permanent rear parking

Ratio Decidendi

Clause 3 of the agreement are conditions precedent; there is no necessary implication that Potters was obliged on execution to apply to Council or notify for a two-way right-of-way for the Trust; Potters did not breach the agreement and its obligations ended when the Trust failed to obtain the consents within the agreed period, so the Trust is not entitled to specific performance or damages and the agreement is unenforceable.

Court Disposition

Judgment for defendant; plaintiff's claims for specific performance and damages dismissed; counterclaim succeeds

Orders

  • Declaration that the right-of-way agreement is unenforceable
  • Order that caveat number 9136703.1 be removed from title 542914