NORTHERN CIVIL CONSULTING ENGINEERS LIMITED v SOVEREIGN STATION TRUSTEE LIMITED [2013] NZHC 2952

NORTHERN CIVIL CONSULTING ENGINEERS LIMITED v SOVEREIGN STATION TRUSTEE LIMITED [2013] NZHC 2952

The court exercised its discretion to adjourn the liquidation application to a defended hearing on 20 November 2013 in Whangarei, but only on strict terms: Sovereign Station must pay $6,000 to Northern Engineers by midday 11 November 2013 and comply with timetabling and evidence directions; failure to pay will...

Source-derived case information.

Citation
[2013] NZHC 2952
Parties
Plaintiff: Northern Civil Consulting Engineers Limited; Defendant: Sovereign Station Trustee Limited
Court
High Court
Jurisdiction
New Zealand
Judgment Date
8 November 2013
Procedural Posture
Application for Liquidation / Adjourned to Defended Hearing (scheduled 20 November 2013)
Outcome
Liquidation application adjourned to a defended hearing on conditions; conditional order to wind up if costs not paid
Legal Topics
Statutory Demand, Presumption of Insolvency, Adjournment on Terms, Costs as Condition of Adjournment, Disputed Debt Procedure
Company Law Insolvency Civil Procedure Statutory Demand Presumption of Insolvency Adjournment on Terms Costs as Condition of Adjournment Disputed Debt Procedure

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Northern Civil Consulting Engineers Limited

Plaintiff

Sovereign Station Trustee Limited

Defendant

Procedural Posture

Application for Liquidation / Adjourned to Defended Hearing (scheduled 20 November 2013)

  1. 1 Whether non-compliance with a statutory demand establishes insolvency of the respondent
  2. 2 Whether the debt is genuinely disputed and therefore precludes a liquidation order without exploration by cross-examination
  3. 3 Whether an adjournment should be granted and on what terms including payment of costs

Ratio Decidendi

The court exercised its discretion to adjourn the liquidation application to a defended hearing on 20 November 2013 in Whangarei, but only on strict terms: Sovereign Station must pay $6,000 to Northern Engineers by midday 11 November 2013 and comply with timetabling and evidence directions; failure to pay will result in an immediate liquidation order to be made later that day.

Court Disposition

Liquidation application adjourned to a defended hearing on conditions; conditional order to wind up if costs not paid

Orders

  • Proceeding adjourned until 10:00am on 20 November 2013 for a defended hearing in Whangarei before Associate Judge Bell
  • Sovereign Station shall pay to the solicitors for Northern Engineers by midday on 11 November 2013 the sum of $6,000 inclusive of disbursements