NORTHLAKE INVESTMENTS LTD v CIVIL CONSTRUCTION LTD [2023] NZHC 2715

NORTHLAKE INVESTMENTS LTD v CIVIL CONSTRUCTION LTD [2023] NZHC 2715

The adjudicator's determination was binding and enforceable under the Construction Contracts Act 2002; Civil was entitled to refer the Covid Claim and the Stage 12 Claim to adjudication (progress payment disputes are recoverable under the Act) and Northlake cannot recover payments made to satisfy a binding...

Source-derived case information.

Citation
[2023] NZHC 2715
Parties
Plaintiff: Northlake Investments Limited; Defendant: Civil Construction Limited
Court
High Court
Jurisdiction
New Zealand
Judgment Date
28 September 2023
Procedural Posture
Construction Contract Dispute (payment/adjudication) / Summary Judgment and Strike Out Applications (high Court)
Outcome
Northlake's summary judgment application dismissed; Civil's summary judgment application dismissed; Northlake's cause of action struck out with leave to amend; case management directions made and costs reserved.
Legal Topics
Construction Contracts Act 2002, NZS 3910:2013 Cl 13 Dispute Resolution, Adjudication Enforceability, Money Had and Received, Summary Judgment, Contractual Time Limits, Progress Payment Schedules
Construction Law Contract Law Civil Procedure Restitution Law Statutory Adjudication Construction Contracts Act 2002 NZS 3910:2013 Cl 13 Dispute Resolution Adjudication Enforceability +4 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 5 Authorities cited 14 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Northlake Investments Limited

Plaintiff

Civil Construction Limited

Defendant

Procedural Posture

Construction Contract Dispute (payment/adjudication) / Summary Judgment and Strike Out Applications (high Court)

  1. 1 Was Civil required to dispute the engineer's decisions under cl 13 of NZS 3910:2013?
  2. 2 If so, did Civil comply with the contractual dispute process in the required manner?
  3. 3 Was the adjudicator's determination binding and enforceable under the Construction Contracts Act 2002?

Ratio Decidendi

The adjudicator's determination was binding and enforceable under the Construction Contracts Act 2002; Civil was entitled to refer the Covid Claim and the Stage 12 Claim to adjudication (progress payment disputes are recoverable under the Act) and Northlake cannot recover payments made to satisfy a binding adjudicator determination as money had and received in the absence of a subsequent final determination disposing of the adjudicator's interim award; the specific contractual interpretation issue in cl 13.1.1 could not be finally determined on the summary application but the court was inclined that cl 13.1.1 contemplates escalation and timely pursuit of disputes and does not render...

Court Disposition

Northlake's summary judgment application dismissed; Civil's summary judgment application dismissed; Northlake's cause of action struck out with leave to amend; case management directions made and costs reserved.

Orders

  • Northlake's application for summary judgment is dismissed.
  • Civil's application for summary judgment is dismissed.