NORTHWEST DEVELOPMENTS LTD v ZHANG, JUNG and SO [2020] NZHC 1151

NORTHWEST DEVELOPMENTS LTD v ZHANG, JUNG and SO [2020] NZHC 1151

Court held Northwest entitled to enforce the Five Owners' Agreement; the20% contractual default interest in clause 42 is not an unenforceable penalty andis recoverable on a daily basis from due dates; the defendants' failure to consentto deposit of the survey plan was an effective cause of Northwest's...

Source-derived case information.

Citation
[2020] NZHC 1151
Parties
Plaintiff: Northwest Developments Ltd; Defendant: Cheng Zhang; Defendant: Jin Kuk Jung; Defendant: Pill Soon So; Third Party / Plaintiff (continued): Sanli Homes Limited; Third Party / Plaintiff (continued): Sanli Group Limited
Court
High Court
Jurisdiction
New Zealand
Judgment Date
28 May 2020
Procedural Posture
Civil Contract and Property Dispute / Judgment After Trial (continued Hearing)
Outcome
Judgment for plaintiff Northwest Developments Ltd against defendantsCheng Zhang, Jin Kuk Jung and Pill Soon So for infrastructure costs, contractualdefault interest and consequential damages; costs awarded to plaintiff subject toseparate determination of solicitor and client costs.
Legal Topics
Infrastructure Cost Allocation, Contractual Default Interest, Penalty Doctrine, Remoteness and Causation of Damages, Specific Performance and Injunctions, Caveats and Survey Plan Deposit, Solicitor and Client Costs
Contract Law Property Law Land Transfer Equity and Specific Performance Commercial Finance Infrastructure Cost Allocation Contractual Default Interest Penalty Doctrine +4 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 5 Authorities cited 16 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Northwest Developments Ltd

Plaintiff

Cheng Zhang

Defendant

Jin Kuk Jung

Defendant

Pill Soon So

Defendant

Sanli Homes Limited

Third Party / Plaintiff (continued)

Sanli Group Limited

Third Party / Plaintiff (continued)

Procedural Posture

Civil Contract and Property Dispute / Judgment After Trial (continued Hearing)

  1. 1 Whether clause 42 (20% p.a.) default interest is enforceable or anunenforceable penalty
  2. 2 Whether defendants' breach in refusing to consent to deposit of survey plancaused Northwest's claimed consequential losses
  3. 3 Whether claimed consequential losses are too remote

Ratio Decidendi

Court held Northwest entitled to enforce the Five Owners' Agreement; the20% contractual default interest in clause 42 is not an unenforceable penalty andis recoverable on a daily basis from due dates; the defendants' failure to consentto deposit of the survey plan was an effective cause of Northwest's consequentialborrowing losses and Northwest is entitled to damages of $1,347,244.81 pluscontractual and statutory interest; solicitor and client costs claim subject toseparate affidavited submissions.

Court Disposition

Judgment for plaintiff Northwest Developments Ltd against defendantsCheng Zhang, Jin Kuk Jung and Pill Soon So for infrastructure costs, contractualdefault interest and consequential damages; costs awarded to plaintiff subject toseparate determination of solicitor and client costs.

Orders

  • Judgment for infrastructure costs of 1178301.71 NZD payable jointly andseverally by the defendants
  • Default interest of 488042.68 NZD to 16 January 2020 awarded to theplaintiff