PRINCIPLE DEVELOPMENTS LTD v SLOTEMAKER [2022] NZHC 2283

PRINCIPLE DEVELOPMENTS LTD v SLOTEMAKER [2022] NZHC 2283

The statutory demand was set aside under s 290(4)(a) because there is a substantial and arguable dispute as to whether PDL breached clause 25.1: the clause reasonably refers to the existing constructed and council‑certified building platform and to earthworks that would alter or reposition the platform or its amenity, whereas the evidence shows remedial earthworks were undertaken adjacent to and to protect the platform and there is no clear change to its physical attributes; therefore it is arguable no debt is owing and the demand must be set aside.

Citation
[2022] NZHC 2283
Parties
Plaintiff: Principle Developments Ltd; Defendant: Dylan Slotemaker
Court
High Court
Jurisdiction
New Zealand
Judgment Date
8 September 2022
Procedural Posture
Application to Set Aside Statutory Demand Under the Companies Act 1993 / Judgment on Interlocutory Application
Outcome
Statutory demand set aside under s 290(4)(a) of the Companies Act 1993
Legal Topics
Statutory Demand, Set Aside, Contract Interpretation, Breach of Contract, Deposit Recovery, Solvency

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Principle Developments Ltd

Plaintiff

Dylan Slotemaker

Defendant

Procedural Posture

Application to Set Aside Statutory Demand Under the Companies Act 1993 / Judgment on Interlocutory Application

  1. 1 Whether vendor breached clause 25.1 (size of building platform)
  2. 2 Whether vendor breached clause 25.1 (earthworks in vicinity)
  3. 3 Whether purchaser validly cancelled agreement for breach of essential term

Ratio Decidendi

The statutory demand was set aside under s 290(4)(a) because there is a substantial and arguable dispute as to whether PDL breached clause 25.1: the clause reasonably refers to the existing constructed and council‑certified building platform and to earthworks that would alter or reposition the platform or its amenity, whereas the evidence shows remedial earthworks were undertaken adjacent to and to protect the platform and there is no clear change to its physical attributes; therefore it is arguable no debt is owing and the demand must be set aside.

Court Disposition

Statutory demand set aside under s 290(4)(a) of the Companies Act 1993

Orders

  • Statutory demand dated 25 March 2022 set aside
  • Parties to confer on costs; if they cannot agree, each may file a memorandum of no longer than five pages within 21 days