SERVICE PAINTING & BUILDING CO PTY LIMITED v PACIFIC INTERNATIONAL HOTEL MANAGEMENT SCHOOL LIMITED [2017] NZHC 850

SERVICE PAINTING & BUILDING CO PTY LIMITED v PACIFIC INTERNATIONAL HOTEL MANAGEMENT SCHOOL LIMITED [2017] NZHC 850

Summary judgment granted to SPB for net NZD 118,646.80 plus statutory interest; the court held clause 3's reference to 'fundamental breach' did not extinguish accrued payment obligations, clause 6 operated to preserve recovery of amounts paid, due or becoming due despite cancellation, the School had affirmed the...

Source-derived case information.

Citation
[2017] NZHC 850
Parties
Plaintiff: Service Painting & Building Co Pty Limited; Defendant: Pacific International Hotel Management School Limited
Court
High Court
Jurisdiction
New Zealand
Judgment Date
2 May 2017
Procedural Posture
Contract Dispute Recovery of Unpaid Instalments Under Painting Contracts / Summary Judgment
Outcome
summary judgment entered in part for plaintiff; residual claims to proceed to trial
Legal Topics
Contract Termination, Fundamental Breach, Contractual Remedies Act 1979 S9, Set Off and Abatement, Implied Terms, Damages, Interest, Summary Judgment
Contract Law Remedies Civil Procedure Commercial Law Contract Termination Fundamental Breach Contractual Remedies Act 1979 S9 Set Off and Abatement +4 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Service Painting & Building Co Pty Limited

Plaintiff

Pacific International Hotel Management School Limited

Defendant

Procedural Posture

Contract Dispute Recovery of Unpaid Instalments Under Painting Contracts / Summary Judgment

  1. 1 Whether the defendant validly terminated the 2009 contract for fundamental breach
  2. 2 Whether clause 3's reference to 'fundamental breach' extinguished plaintiff's accrued payment rights
  3. 3 Whether clause 6 modified statutory cancellation consequences under the Contractual Remedies Act 1979

Ratio Decidendi

Summary judgment granted to SPB for net NZD 118,646.80 plus statutory interest; the court held clause 3's reference to 'fundamental breach' did not extinguish accrued payment obligations, clause 6 operated to preserve recovery of amounts paid, due or becoming due despite cancellation, the School had affirmed the contract by conduct and delay so its purported early termination was ineffective, the School was entitled only to a limited arguable set-off for defective or missed maintenance work ($13,800 allowed), and remaining disputed issues proceed to trial.

Court Disposition

summary judgment entered in part for plaintiff; residual claims to proceed to trial

Orders

  • Judgment is entered for Service Painting & Building Co Pty Limited in the sum of NZD 118,646.80 together with interest on that sum at the rate of five per cent per annum calculated from 29 October 2015 down to the date of this judgment.
  • To the extent that SPB's claims exceed that figure, those claims are to proceed to trial.