SPX FLOW TECHNOLOGY NZ LTD v GAS 1 LTD [2017] NZHC 2049

SPX FLOW TECHNOLOGY NZ LTD v GAS 1 LTD [2017] NZHC 2049

The Court held SPX was entitled to the agreed milestone payments because Gardians/Gas 1, by adopting a revised production schedule, allowing SPX to be prevented from undertaking the completion tests and ultimately selling the plant, waived the contractual testing conditions and/or prevented completion of the tests...

Source-derived case information.

Citation
[2017] NZHC 2049
Parties
Plaintiff: SPX Flow Technology New Zealand Limited; Defendant: Gas 1 Limited (formerly Gardians Limited)
Court
High Court
Jurisdiction
New Zealand
Judgment Date
25 August 2017
Procedural Posture
Contract (construction/commercial) / High Court Judgment (trial)
Outcome
Judgment for plaintiff SPX Flow Technology New Zealand Limited against defendant Gas 1 Limited for outstanding contractual payments, with orders for return of performance security and issuance of performance certificate; costs and interest reserved
Legal Topics
Breach of Contract, Variation and Settlement Deed, Waiver, Proprietary Estoppel/estoppel by Representation, Deemed Performance, FIDIC Interpretation, Substantial Performance, Performance Security, Misrepresentation Under Fair Trading Act, Liquidated Damages
Contract Law Construction Law Commercial Law Competition/fair Trading Law Civil Procedure Breach of Contract Variation and Settlement Deed Waiver +7 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 5 Authorities cited 9 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

SPX Flow Technology New Zealand Limited

Plaintiff

Gas 1 Limited (formerly Gardians Limited)

Defendant

Procedural Posture

Contract (construction/commercial) / High Court Judgment (trial)

  1. 1 Whether plaintiff was entitled to Phases 1–4 payments under the March 2013 term sheet variation
  2. 2 Whether defendant was induced by misrepresentation to enter the settlement (Fair Trading Act claim)
  3. 3 Whether defendant waived the right to require formal Phase 1/3 tests by adopting a new production schedule and selling the plant

Ratio Decidendi

The Court held SPX was entitled to the agreed milestone payments because Gardians/Gas 1, by adopting a revised production schedule, allowing SPX to be prevented from undertaking the completion tests and ultimately selling the plant, waived the contractual testing conditions and/or prevented completion of the tests so that under the parties' incorporated FIDIC terms the tests are deemed satisfied; SPX had substantially performed Phase 2 subject to a deduction for outstanding remedial work; accordingly judgment was entered for SPX for the adjusted contractual balance and the performance security was to be returned.

Court Disposition

Judgment for plaintiff SPX Flow Technology New Zealand Limited against defendant Gas 1 Limited for outstanding contractual payments, with orders for return of performance security and issuance of performance certificate; costs and interest reserved

Orders

  • Judgment for SPX Flow Technology New Zealand Limited against Gas 1 Limited for NZD 4,512,661 plus GST (Phases 1–4, net of agreed deductions)
  • Gardians/Gas 1 Limited to issue the FIDIC performance certificate as at 20 December 2013