TARANAKI GALVANISERS LTD v UDDERFIELD LTD & ORS [2018] NZCA 297

TARANAKI GALVANISERS LTD v UDDERFIELD LTD & ORS [2018] NZCA 297

The Court held the presumption under r 15.23 was not displaced: the discontinuing plaintiff (Udderfield) must pay the defendant's (Taranaki Galvanisers) High Court costs because Udderfield sued an entity that did not do the work and the proceedings were time-barred under Building Act s 393; the Court declined to...

Source-derived case information.

Citation
[2018] NZCA 297
Parties
Appellant: Taranaki Galvanisers Limited; First Respondent: Udderfield Limited; Second Respondent: John Chapman; Third Respondent: Mike Childs Builders Limited; Fourth Respondent: J D Engineering Limited
Court
Court of Appeal
Jurisdiction
New Zealand
Judgment Date
7 August 2018
Procedural Posture
Appeal (costs) / Court of Appeal Judgment on Costs
Outcome
Appeal allowed in part: High Court order varied so Udderfield to pay Taranaki Galvanisers' High Court costs; no change to orders concerning third parties; Udderfield to pay Court of Appeal costs to Galvanisers on a standard appeal band A basis with usual disbursements.
Legal Topics
Costs, Discontinuance, Third Party Joinder, Limitation Period, Building Act S393
Civil Procedure Construction Law Tort (negligence) Statutory Limitation Costs Discontinuance Third Party Joinder Limitation Period +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 12 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Taranaki Galvanisers Limited

Appellant

Udderfield Limited

First Respondent

John Chapman

Second Respondent

Mike Childs Builders Limited

Third Respondent

J D Engineering Limited

Fourth Respondent

Procedural Posture

Appeal (costs) / Court of Appeal Judgment on Costs

  1. 1 Whether the presumption under High Court Rules r 15.23 that a discontinuing plaintiff pays the defendant's costs was displaced
  2. 2 Whether the defendant or the discontinuing plaintiff should bear the costs of third parties joined by the defendant
  3. 3 Effect of the Building Act 2004 s 393 limitation period and the fact the defendant did not exist when the work was done

Ratio Decidendi

The Court held the presumption under r 15.23 was not displaced: the discontinuing plaintiff (Udderfield) must pay the defendant's (Taranaki Galvanisers) High Court costs because Udderfield sued an entity that did not do the work and the proceedings were time-barred under Building Act s 393; the Court declined to interfere with the High Court's discretionary apportionment regarding third party costs and left those orders unchanged.

Court Disposition

Appeal allowed in part: High Court order varied so Udderfield to pay Taranaki Galvanisers' High Court costs; no change to orders concerning third parties; Udderfield to pay Court of Appeal costs to Galvanisers on a standard appeal band A basis with usual disbursements.

Orders

  • Appeal allowed in part
  • Udderfield Limited to pay Taranaki Galvanisers Limited's costs in the High Court