VECTOR LIMITED v TRANSPOWER NEW ZEALAND LIMITED & ANOR [2014] NZHC 3411 [24 December 2014]
The TPM's definitions are to be applied in the present tense: asset classification is determined by the electrical configuration at the relevant time (whether the asset is electrically connected in a loop), not by the subjective intentions or future plans for staged commissioning; this interpretation is consistent with the Authority's statutory objective and promotes certainty and correct pricing signals; exceptional cases should be addressed through the statutory exemption process.
- Citation
- [2014] NZHC 3411
- Parties
- Plaintiff: Vector Limited; First Defendant: Transpower New Zealand Limited; Second Defendant: Electricity Authority
- Court
- High Court
- Jurisdiction
- New Zealand
- Judgment Date
- 7 January 2013
- Procedural Posture
- Civil Statutory Interpretation / Judgment
- Outcome
- Application dismissed
- Legal Topics
- Transmission Pricing, Connection Vs Interconnection Assets, Exemption Under S11(2), Treatment of Staged Commissioning, Allocation of Transmission Costs
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Vector Limited
Plaintiff
Transpower New Zealand Limited
First Defendant
Electricity Authority
Second Defendant
Procedural Posture
Civil Statutory Interpretation / Judgment
Legal Issues
- 1 Whether the Albany–Wairau Road link was a connection asset or interconnection asset under the TPM during the period 25 May 2013 to 26 February 2014
- 2 Whether the TPM's definition of a loop should be read with a purposive gloss 'under normal operating circumstances' or intention-based test
- 3 Whether the Electricity Authority's refusal to grant an exemption under s11(2) was unlawful or unreasonable
Ratio Decidendi
The TPM's definitions are to be applied in the present tense: asset classification is determined by the electrical configuration at the relevant time (whether the asset is electrically connected in a loop), not by the subjective intentions or future plans for staged commissioning; this interpretation is consistent with the Authority's statutory objective and promotes certainty and correct pricing signals; exceptional cases should be addressed through the statutory exemption process.
Court Disposition
Application dismissed
Orders
- Application dismissed
- Electricity Authority entitled to costs on a 2B basis
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment