Morrow v FP McCann Ltd [2007] NIIT 122_07 (24 September 2007)

Morrow v FP McCann Ltd [2007] NIIT 122_07 (24 September 2007)

The claimant failed to comply with the statutory requirement to wait 28 days after lodging a grievance before presenting a claim, rendering the claim inadmissible.

Citation
[2007] NIIT 122_07
Parties
Claimant: Ronald Morrow; Respondent: F P McCann Ltd
Jurisdiction
Northern Ireland
Judgment Date
24 September 2007
Procedural Posture
Industrial Tribunal / Pre Hearing Review
Outcome
Claim dismissed as inadmissible
Legal Topics
Grievance Procedure, Time Limits for Claims, Employment (northern Ireland) Order 2003

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2
Sign in to unlock

Parties

Ronald Morrow

Claimant

F P McCann Ltd

Respondent

Procedural Posture

Industrial Tribunal / Pre Hearing Review

  1. 1 Whether the claimant complied with the statutory grievance procedure and time limits under Article 19(2) and (3) of the Employment (Northern Ireland) Order 2003

Ratio Decidendi

The claimant failed to comply with the statutory requirement to wait 28 days after lodging a grievance before presenting a claim, rendering the claim inadmissible.

Court Disposition

Claim dismissed as inadmissible