Bickerstaff v RMS Cash Solutions Limited t/a... (Breach of Contract) [2021] NIIT 02058_20IT (24 March 2021)

Bickerstaff v RMS Cash Solutions Limited t/a... (Breach of Contract) [2021] NIIT 02058_20IT (24 March 2021)

The claim was struck out because the claimant failed to comply with the Unless Order dated 18 December 2020, which required a response by 28 January 2021.

Citation
[2021] NIIT 02058_20IT
Parties
Claimant: Claimant; Respondent: Respondent
Jurisdiction
Northern Ireland
Judgment Date
24 March 2021
Procedural Posture
Employment / Striking Out of Claim
Outcome
claim struck out
Legal Topics
Unless Order, Striking Out, Non Compliance

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Party arguments 2
Sign in to unlock

Parties

Claimant

Claimant

Respondent

Respondent

Procedural Posture

Employment / Striking Out of Claim

  1. 1 Whether the claim should be struck out for failure to comply with an Unless Order

Ratio Decidendi

The claim was struck out because the claimant failed to comply with the Unless Order dated 18 December 2020, which required a response by 28 January 2021.

Court Disposition

claim struck out

Orders

  • The claim is struck out.