Bradley v SJ McIntyre Builders Ltd [2012] NIIT 00671_12IT (24 July 2012)
The amendment to include a breach of contract claim for notice pay arises from the same facts as the original claim and is permissible. The respondent failed to comply with statutory minimum notice requirements, entitling the claimant to 12 weeks' notice pay.
- Citation
- [2012] NIIT 00671_12IT
- Parties
- Claimant: Thomas George Bradley; Respondent: SJ McIntyre Builders Ltd
- Jurisdiction
- Northern Ireland
- Judgment Date
- 24 July 2012
- Procedural Posture
- Industrial Tribunal / Final Decision
- Outcome
- Claimant entitled to notice payment.
- Legal Topics
- Redundancy, Notice Pay, Breach of Contract, Amendment of Claim
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Thomas George Bradley
Claimant
SJ McIntyre Builders Ltd
Respondent
Procedural Posture
Industrial Tribunal / Final Decision
Legal Issues
- 1 Whether the claimant's claim should be amended to include a breach of contract claim for notice pay
- 2 If so, the amount of notice pay due to the claimant
Ratio Decidendi
The amendment to include a breach of contract claim for notice pay arises from the same facts as the original claim and is permissible. The respondent failed to comply with statutory minimum notice requirements, entitling the claimant to 12 weeks' notice pay.
Court Disposition
Claimant entitled to notice payment.
Orders
- Respondent to pay claimant £3342.60 as notice payment.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment