Aegis Wind Turbines Limited Aegis Power Plc (In Liquidatio... v Patrick Moran Patrick Moran (Breach of Contract) [2022] NIIT 01197_16IT (11 April 2022)

Aegis Wind Turbines Limited Aegis Power Plc (In Liquidatio... v Patrick Moran Patrick Moran (Breach of Contract) [2022] NIIT 01197_16IT (11 April 2022)

The claim was struck out because the claimant failed to comply with the Order dated 4 March 2022 by the deadline of 5 April 2022.

Citation
[2022] NIIT 01197_16IT
Parties
Claimant: Unknown Claimant; Respondent: Unknown Respondent
Jurisdiction
Northern Ireland
Judgment Date
11 April 2022
Procedural Posture
Employment Claim / Judgment
Outcome
claim struck out
Legal Topics
Strike Out, Non Compliance With Court Order

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 1 Party arguments 1
Sign in to unlock

Parties

Unknown Claimant

Claimant

Unknown Respondent

Respondent

Procedural Posture

Employment Claim / Judgment

  1. 1 Whether the claim should be struck out for failure to comply with court order

Ratio Decidendi

The claim was struck out because the claimant failed to comply with the Order dated 4 March 2022 by the deadline of 5 April 2022.

Court Disposition

claim struck out

Orders

  • The claim is struck out.