McCann v Vector Facilities Management Wallace Contracts (NI) Ltd Vector Facilities Management Wallace Contracts (NI) Limited [2012] NIIT 01248_11IT (06 January 2012)
Leave to amend claim forms to include Regulation 15 claims against Vector is granted as refusal would cause greater prejudice to claimants than any hardship to respondents; delay was short and did not diminish respondents' ability to contest claims.
- Citation
- [2012] NIIT 01248_11IT
- Parties
- Claimant: John Gerard McCann; Claimant: Jonathan McCann; Respondent: Vector Facilities Management; Respondent: Wallace Contracts (NI) Limited
- Jurisdiction
- Northern Ireland
- Judgment Date
- 06 January 2012
- Procedural Posture
- Industrial Tribunal / Pre Hearing Review on Leave to Amend Claim Form
- Outcome
- Leave to amend granted in part, deferred in part.
- Legal Topics
- Transfer of Undertakings, Information and Consultation, Unfair Dismissal, Amendment of Claim, Service Provision Change
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
John Gerard McCann
Claimant
Jonathan McCann
Claimant
Vector Facilities Management
Respondent
Wallace Contracts (NI) Limited
Respondent
Procedural Posture
Industrial Tribunal / Pre Hearing Review on Leave to Amend Claim Form
Legal Issues
- 1 Whether claimants should be granted leave to amend claim forms to include claims under Regulation 15 of TUPER and SPCR against respondents
- 2 Whether Regulation 15 claims are time-barred
- 3 Whether transferee (Wallace) is subject to Regulation 13 duties for employees not employed prior to transfer
Ratio Decidendi
Leave to amend claim forms to include Regulation 15 claims against Vector is granted as refusal would cause greater prejudice to claimants than any hardship to respondents; delay was short and did not diminish respondents' ability to contest claims.
Court Disposition
Leave to amend granted in part, deferred in part.
Orders
- Each claimant is granted leave to amend claim form to include Regulation 15 claims against Vector Facilities Management.
- Determination on leave to amend claim form to include Regulation 15 claims against Wallace Contracts (NI) Limited is deferred.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment