AKARERE KA GATSIBO v. V.CO LTD
The Supreme Court held that each contract extension constituted a new contract for additional work and time, entitling V.CO Ltd to payment at the agreed monthly rate for the additional period. The fixed price clause applied only to the original 24-month period. Refusal to pay for additional work would unjustly enrich the applicant and violate the principle of good faith in contract execution. The Court recalculated the amount due based on the actual period of additional work performed.
- Citation
- RLR V.1-2025
- Parties
- Applicant: Akarere ka Gatsibo; Respondent: V.CO Ltd
- Court
- Supreme Court
- Jurisdiction
- Rwanda
- Judgment Date
- 26 May 2023
- Case Number
- RS/INJUST/RCOM 00007/2022/SC
- Procedural Posture
- Commercial Contract Dispute / Supreme Court Review on Grounds of Injustice
- Outcome
- Applicant's claim for review on grounds of injustice dismissed; respondent entitled to payment for additional work.
- Legal Topics
- Contract Extensions, Payment for Additional Work, Interpretation of Contract Terms, Fixed Price Contracts, Public Procurement Procedures
- Source Language
- rw
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Akarere ka Gatsibo
Applicant
V.CO Ltd
Respondent
Procedural Posture
Commercial Contract Dispute / Supreme Court Review on Grounds of Injustice
Legal Issues
- 1 Whether V.CO Ltd is entitled to payment for additional work performed beyond the original contract period
- 2 Whether payment for additional work constitutes an impermissible change to the agreed contract price
- 3 Whether the contract extensions constituted new contracts or mere time extensions
Ratio Decidendi
The Supreme Court held that each contract extension constituted a new contract for additional work and time, entitling V.CO Ltd to payment at the agreed monthly rate for the additional period. The fixed price clause applied only to the original 24-month period. Refusal to pay for additional work would unjustly enrich the applicant and violate the principle of good faith in contract execution. The Court recalculated the amount due based on the actual period of additional work performed.
Court Disposition
Applicant's claim for review on grounds of injustice dismissed; respondent entitled to payment for additional work.
Orders
- Akarere ka Gatsibo to pay V.CO Ltd 24,530,133 Frw for additional work performed beyond the original contract period.
- Akarere ka Gatsibo to pay V.CO Ltd 300,000 Frw as litigation costs and 500,000 Frw as advocate's fees, totaling 800,000 Frw.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment