DICKIE & MOORE LTD AGAINST RONALD JAMES McLEISH AND OTHERS [2020] ScotCS CSIH_38 (30 June 2020)
The court held that the valid parts of an adjudicator’s decision may be severed and enforced if they are not tainted by the invalid parts, even in a single dispute adjudication. The test is whether a core nucleus of the decision can be safely enforced. The commercial judge was correct to enforce the valid parts of the award, as the claims for measured work and additional works were independent of the extension of time and loss and expense claims, which had not crystallized.
- Citation
- [2020] ScotCS CSIH_38
- Parties
- Pursuer and Respondent: Dickie & Moore Limited; Defenders and Reclaimers: Ronald James McLeish, Mrs Diane McLeish and Catriona Watt as Trustees of the Lauren McLeish Discretionary Trust
- Jurisdiction
- Scotland
- Judgment Date
- 30 June 2020
- Procedural Posture
- Commercial Enforcement of Adjudicator's Award (construction Contract) / Appeal (reclaiming Motion) in the Inner House, Court of Session
- Outcome
- Reclaiming motion refused; commercial judge's decision affirmed.
- Legal Topics
- Adjudication Enforcement, Jurisdiction of Adjudicator, Severance of Adjudicator's Decision, Crystallization of Disputes, Natural Justice in Adjudication
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Dickie & Moore Limited
Pursuer and Respondent
Ronald James McLeish, Mrs Diane McLeish and Catriona Watt as Trustees of the Lauren McLeish Discretionary Trust
Defenders and Reclaimers
Procedural Posture
Commercial Enforcement of Adjudicator's Award (construction Contract) / Appeal (reclaiming Motion) in the Inner House, Court of Session
Legal Issues
- 1 Whether parts of an adjudicator’s decision that are within jurisdiction can be severed and enforced when other parts are ultra vires due to lack of crystallization of dispute
- 2 Whether the existence of a single dispute precludes severance of an adjudicator’s decision
- 3 Whether the commercial judge erred in enforcing only the valid parts of the adjudicator’s award
Ratio Decidendi
The court held that the valid parts of an adjudicator’s decision may be severed and enforced if they are not tainted by the invalid parts, even in a single dispute adjudication. The test is whether a core nucleus of the decision can be safely enforced. The commercial judge was correct to enforce the valid parts of the award, as the claims for measured work and additional works were independent of the extension of time and loss and expense claims, which had not crystallized.
Court Disposition
Reclaiming motion refused; commercial judge's decision affirmed.
Orders
- The valid and severable parts of the adjudicator’s award are enforced.
- The extension of time and associated loss and expense awards are not enforced.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment