CRIMOND ESTATES LTD AGAINST MILE END DEVELOPMENTS LTD [2021] ScotCS CSOH_26 (12 March 2021)
MEDL was not entitled to terminate the agreement under clause 6.2.7 because, by their conduct, the parties had dispensed with the requirement for written approval of excess costs. MEDL's termination was therefore a breach of contract. The requirement for written approval was varied by the parties' consistent practice of approving costs through meetings and correspondence, and it would be contrary to commercial sense to allow MEDL to rely on costs they had agreed to as a ground for termination.
- Citation
- [2021] ScotCS CSOH_26
- Parties
- Pursuer: Crimond Estates Limited; Defender: Mile End Developments Limited
- Jurisdiction
- Scotland
- Judgment Date
- 12 March 2021
- Procedural Posture
- Commercial Action (breach of Contract) / Proof Before Answer (judgment)
- Outcome
- For the pursuer (CEL); MEDL's termination was unlawful and CEL is entitled to damages for breach of contract.
- Legal Topics
- Breach of Contract, Project Management Agreements, Termination Clauses, Waiver, Damages Assessment
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Crimond Estates Limited
Pursuer
Mile End Developments Limited
Defender
Procedural Posture
Commercial Action (breach of Contract) / Proof Before Answer (judgment)
Legal Issues
- 1 Whether MEDL was entitled to terminate the project management agreement under clause 6.2.7
- 2 Whether excess costs were approved in writing or by conduct
- 3 Whether MEDL waived its right to terminate
Ratio Decidendi
MEDL was not entitled to terminate the agreement under clause 6.2.7 because, by their conduct, the parties had dispensed with the requirement for written approval of excess costs. MEDL's termination was therefore a breach of contract. The requirement for written approval was varied by the parties' consistent practice of approving costs through meetings and correspondence, and it would be contrary to commercial sense to allow MEDL to rely on costs they had agreed to as a ground for termination.
Court Disposition
For the pursuer (CEL); MEDL's termination was unlawful and CEL is entitled to damages for breach of contract.
Orders
- Declaration that MEDL was in breach of contract by terminating the agreement on 18 November 2016.
- CEL entitled to damages to be assessed based on actual sales and costs, not projections as at breach date.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment