Forrest v. Scottish County Investment Co., Ltd [1914] ScotLR 66 (17 November 1914)
The contractor deviated from the contract specifications regarding the dimensions of rybats and the use of concrete instead of rubble, but the employer accepted the completed work, did not seek rectification, and suffered no proven loss. The architect's approval did not authorize deviation from clear contract terms, but in the absence of a claim for damages or rectification, the contractor is entitled to the contract price, less minor deductions for uncompleted details.
- Citation
- [1914] ScotLR 66
- Parties
- Pursuer: Elphinstone Forrest; Defender: Scottish County Investment Company, Limited
- Jurisdiction
- Scotland
- Judgment Date
- 17 November 1914
- Procedural Posture
- Building Contract Dispute / Inner House, First Division, Court of Session (appeal/reclaiming Motion)
- Outcome
- Pursuer entitled to recover contract balance, less minor deduction; interlocutor of Lord Ordinary adhered to (majority decision).
- Legal Topics
- Building Contracts, Deviation From Contract, Architect's Authority, Remedies for Breach, Quantum Lucratus, Damages, Acceptance of Work
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Elphinstone Forrest
Pursuer
Scottish County Investment Company, Limited
Defender
Procedural Posture
Building Contract Dispute / Inner House, First Division, Court of Session (appeal/reclaiming Motion)
Legal Issues
- 1 Whether the contractor's deviation from specified dimensions in the contract, with architect's approval, disentitles him from recovering the contract price.
- 2 Whether the architect had authority to approve deviations from the contract specifications.
- 3 What remedy is available to the employer when work is accepted but not strictly conforming to contract.
Ratio Decidendi
The contractor deviated from the contract specifications regarding the dimensions of rybats and the use of concrete instead of rubble, but the employer accepted the completed work, did not seek rectification, and suffered no proven loss. The architect's approval did not authorize deviation from clear contract terms, but in the absence of a claim for damages or rectification, the contractor is entitled to the contract price, less minor deductions for uncompleted details.
Court Disposition
Pursuer entitled to recover contract balance, less minor deduction; interlocutor of Lord Ordinary adhered to (majority decision).
Orders
- Decree for pursuer for £633, 16s. less £5 for minor uncompleted work.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment