Emcor Drake And Scull Ltd v. Edinburgh Royal Joint Venture& Ors [2005] ScotCS CSOH_139 (28 October 2005)
Clause 1.01 of the Schedule of Notes/Clarifications, as incorporated in the subcontract, referred only to the spatial co-ordination of services in design drawings with CA status, not to detailed installation drawings. The contract placed responsibility for detailed co-ordination and working drawings on the pursuers. No warranty was granted by the defenders that the tender drawings were sufficiently developed for immediate installation. Evidence relating to pre-contract negotiations and deleted tender provisions was inadmissible for contractual interpretation.
- Citation
- [2005] ScotCS CSOH_139
- Parties
- Pursuer: Emcor Drake & Scull Limited; First Defender: Edinburgh Royal Joint Venture; Second Defender: Balfour Beatty Construction Limited; Third Defender: Haden Young Limited; Fourth Defender: Morrison Construction Limited
- Jurisdiction
- Scotland
- Judgment Date
- 28 October 2005
- Procedural Posture
- Commercial Construction Contract Dispute / Proof Before Answer (preliminary Determination of Warranty Issue)
- Outcome
- Declarator refused; pursuers not entitled to warranty as claimed.
- Legal Topics
- Contractual Interpretation, Warranties, Tender Documentation, Subcontractor Obligations, Variation Claims
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Emcor Drake & Scull Limited
Pursuer
Edinburgh Royal Joint Venture
First Defender
Balfour Beatty Construction Limited
Second Defender
Haden Young Limited
Third Defender
Morrison Construction Limited
Fourth Defender
Procedural Posture
Commercial Construction Contract Dispute / Proof Before Answer (preliminary Determination of Warranty Issue)
Legal Issues
- 1 Whether the defenders warranted that the vast majority of tender drawings were fully co-ordinated and approved for construction
- 2 Proper construction of clause 1.01 of the Schedule of Notes/Clarifications
- 3 Admissibility of evidence relating to pre-contract negotiations
Ratio Decidendi
Clause 1.01 of the Schedule of Notes/Clarifications, as incorporated in the subcontract, referred only to the spatial co-ordination of services in design drawings with CA status, not to detailed installation drawings. The contract placed responsibility for detailed co-ordination and working drawings on the pursuers. No warranty was granted by the defenders that the tender drawings were sufficiently developed for immediate installation. Evidence relating to pre-contract negotiations and deleted tender provisions was inadmissible for contractual interpretation.
Court Disposition
Declarator refused; pursuers not entitled to warranty as claimed.
Orders
- Proof before answer concluded; pursuers' claim for warranty rejected; parties to proceed on remaining issues if any.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment