TARMAC TRADING LIMITED AGAINST NETWORK RAIL INFRASTRUCTURE LIMITED [2018] ScotCS CSOH_33 (06 April 2018)
The court held that the terms sought to be implied by the pursuer were not necessary to give the Undertaking business efficacy. The Undertaking was effective on its express terms, which referred only to the works authorised by the Bill (Work No. 27) and did not include any obligation to provide a connecting road or track to the quarry. The absence of any express provision for such a connection, despite detailed negotiation and professional involvement, indicated that no such obligation was intended. The contract was commercially and practically coherent without the implied terms, and the pursuer’s claim failed.
- Citation
- [2018] ScotCS CSOH_33
- Parties
- Pursuer: Tarmac Trading Limited; Defender: Network Rail Infrastructure Limited
- Jurisdiction
- Scotland
- Judgment Date
- 06 April 2018
- Procedural Posture
- Commercial Action for Breach of Contract / Proof Before Answer on Preliminary Issue of Implied Terms
- Outcome
- Pursuer's case dismissed
- Legal Topics
- Implied Terms, Business Efficacy, Construction of Contracts, Damages for Breach of Contract
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Tarmac Trading Limited
Pursuer
Network Rail Infrastructure Limited
Defender
Procedural Posture
Commercial Action for Breach of Contract / Proof Before Answer on Preliminary Issue of Implied Terms
Legal Issues
- 1 Whether it was necessary to imply terms into the Undertaking to provide continued access to Blairhill Quarry for business efficacy
- 2 Whether the Undertaking required Network Rail to provide a replacement access route to the quarry
Ratio Decidendi
The court held that the terms sought to be implied by the pursuer were not necessary to give the Undertaking business efficacy. The Undertaking was effective on its express terms, which referred only to the works authorised by the Bill (Work No. 27) and did not include any obligation to provide a connecting road or track to the quarry. The absence of any express provision for such a connection, despite detailed negotiation and professional involvement, indicated that no such obligation was intended. The contract was commercially and practically coherent without the implied terms, and the pursuer’s claim failed.
Court Disposition
Pursuer's case dismissed
Orders
- The questions for the court are answered in the negative; no terms are to be implied into the Undertaking as sought by the pursuer.
- No damages awarded.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment