Claddagh Steamship Co. Ltd (Owners of S.S. "Claddagh" and S.S. "Factor") v. Thomas C. Steven & Co. [1919] ScotLR 195 (19 December 1919)
The sellers could not enforce the contract for the 'Claddagh' because Government requisition prevented them from delivering actual possession as required by the contract; risk remained with sellers until delivery. The contracts for 'Claddagh' and 'Factor' were not interdependent, as no such condition was expressed or implied in the written agreements; buyers' motive for purchasing both ships was irrelevant. The defenders were in breach of contract for refusing to take delivery of the 'Factor', and liable for damages.
- Citation
- [1919] ScotLR 195
- Parties
- Pursuer: Claddagh Steamship Company Limited (Owners of S. S. 'Claddagh' and S. S. 'Factor'); Defender: Thomas C. Steven & Company
- Jurisdiction
- Scotland
- Judgment Date
- 19 December 1919
- Procedural Posture
- Conjoined Actions for Damages for Breach of Contract / Appeal From Lord Ordinary's Interlocutor, Inner House Judgment
- Outcome
- Pursuers' claim regarding 'Claddagh' dismissed; pursuers succeed regarding 'Factor', damages to be assessed if not agreed.
- Legal Topics
- Interdependence of Contracts, Government Requisition, Delivery Under Contract, Damages for Breach of Contract
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Claddagh Steamship Company Limited (Owners of S. S. 'Claddagh' and S. S. 'Factor')
Pursuer
Thomas C. Steven & Company
Defender
Procedural Posture
Conjoined Actions for Damages for Breach of Contract / Appeal From Lord Ordinary's Interlocutor, Inner House Judgment
Legal Issues
- 1 Whether sellers could enforce contract for sale of 'Claddagh' after Government requisition prevented delivery
- 2 Whether contracts for 'Claddagh' and 'Factor' were interdependent, entitling buyers to refuse delivery of both if one could not be delivered
Ratio Decidendi
The sellers could not enforce the contract for the 'Claddagh' because Government requisition prevented them from delivering actual possession as required by the contract; risk remained with sellers until delivery. The contracts for 'Claddagh' and 'Factor' were not interdependent, as no such condition was expressed or implied in the written agreements; buyers' motive for purchasing both ships was irrelevant. The defenders were in breach of contract for refusing to take delivery of the 'Factor', and liable for damages.
Court Disposition
Pursuers' claim regarding 'Claddagh' dismissed; pursuers succeed regarding 'Factor', damages to be assessed if not agreed.
Orders
- Affirm Lord Ordinary's interlocutor dismissing 'Claddagh' action.
- Reverse Lord Ordinary's interlocutor in 'Factor' action; defenders liable for damages, remit to Lord Ordinary for assessment if parties do not agree.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment