Maxi Construction Management Ltd v Mortons Rolls Ltd [2001] ScotCS 199 (7 August 2001)
The pursuers' Interim Valuation No. 10 did not constitute a valid claim by the payee under the Scheme for Construction Contracts because it was an application for agreement of valuation, not a claim for payment, and it failed to specify the basis of calculation for several items as required by the Scheme. Therefore, the pursuers were not entitled to decree de plano for the interim payment sought.
- Citation
- [2001] ScotCS 199
- Parties
- Pursuer: Maxi Construction Management Limited; Defender: Mortons Rolls Limited
- Jurisdiction
- Scotland
- Judgment Date
- 07 August 2001
- Procedural Posture
- Civil (construction Contract Dispute) / Outer House, Court of Session – Opinion on Pleadings/interim Payment Application
- Outcome
- Action dismissed (subject to further order)
- Legal Topics
- Interim Payments, Construction Contracts, Statutory Payment Mechanisms, Contract Interpretation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Maxi Construction Management Limited
Pursuer
Mortons Rolls Limited
Defender
Procedural Posture
Civil (construction Contract Dispute) / Outer House, Court of Session – Opinion on Pleadings/interim Payment Application
Legal Issues
- 1 Whether the document submitted by the pursuers constituted a valid application for interim payment or claim by the payee under the contract or statutory scheme
- 2 Whether the contract incorporated the amended Clause 30 regarding payment provisions
- 3 Whether the contract or the statutory Scheme for Construction Contracts applied to the payment process
Ratio Decidendi
The pursuers' Interim Valuation No. 10 did not constitute a valid claim by the payee under the Scheme for Construction Contracts because it was an application for agreement of valuation, not a claim for payment, and it failed to specify the basis of calculation for several items as required by the Scheme. Therefore, the pursuers were not entitled to decree de plano for the interim payment sought.
Court Disposition
Action dismissed (subject to further order)
Orders
- Sustain the defenders' first plea-in-law and dismiss the action, subject to a By Order hearing before final disposal.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment