Carillion Utility Services Ltd v SP Power Systems Ltd [2011] ScotCS CSOH_138 (18 August 2011)
The contract does not provide that lamping and guarding costs when Carillion's personnel were not on site are in all circumstances included in the rates for works. Item 26 of the Schedule applies to lamping and guarding of joint bays when not otherwise covered by other rates. The claim is not irrelevant and should proceed to proof.
- Citation
- [2011] ScotCS CSOH_138
- Parties
- Pursuer: Carillion Utility Services Limited; Defender: SP Power Systems Limited
- Jurisdiction
- Scotland
- Judgment Date
- 18 August 2011
- Procedural Posture
- Commercial Contract Dispute / Interlocutory Decision on Relevancy (motion to Dismiss)
- Outcome
- Defender's motion to dismiss refused; action to proceed to further procedure.
- Legal Topics
- Interpretation of Contract Terms, Payment for Works Under Framework Agreements, Obligations Under Statutory Regulations, Scope of Inclusive Rates in Construction Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Carillion Utility Services Limited
Pursuer
SP Power Systems Limited
Defender
Procedural Posture
Commercial Contract Dispute / Interlocutory Decision on Relevancy (motion to Dismiss)
Legal Issues
- 1 Whether the contract entitles Carillion to payment for lamping and guarding during periods when its personnel were not on site (the 'repair period')
- 2 Whether the inclusive rates in the contract cover lamping and guarding during all periods of open excavation
- 3 Whether Item 26 of the Schedule applies to lamping and guarding during the repair period
Ratio Decidendi
The contract does not provide that lamping and guarding costs when Carillion's personnel were not on site are in all circumstances included in the rates for works. Item 26 of the Schedule applies to lamping and guarding of joint bays when not otherwise covered by other rates. The claim is not irrelevant and should proceed to proof.
Court Disposition
Defender's motion to dismiss refused; action to proceed to further procedure.
Orders
- No averments deleted at this stage; parties to consider pleadings in light of findings.
- Case to be put out by order to hear parties on further procedure.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment