Elmford Ltd v. McLaglan Investments Ltd [2005] ScotCS CSOH_81 (23 June 2005)
The defenders were contractually obliged under the missives to construct the internal distributor road and roundabout up to the boundary with the Non-Food Retail Site, as indicated on the attached plan. The obligation was not satisfied by terminating the road short of the boundary. The Deed of Conditions did not suspend or qualify this obligation, and clause 7 merely provided for further deeds if necessary to give effect to the servitude rights, not for further substantive agreement on road construction.
- Citation
- [2005] ScotCS CSOH_81
- Parties
- Pursuer: Elmford Limited; Defender: McLagan Investments Limited
- Jurisdiction
- Scotland
- Judgment Date
- 23 June 2005
- Procedural Posture
- Commercial Property Dispute / Judgment After Proof Before Answer
- Outcome
- Decree granted in favour of the pursuers for declarator and specific implement as per conclusions 1 to 3; decree refused at this stage for conclusion 4, with leave reserved to apply for further orders if necessary.
- Legal Topics
- Interpretation of Missives, Obligations in Land Sale, Servitude Rights, Specific Implement, Declarator
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Elmford Limited
Pursuer
McLagan Investments Limited
Defender
Procedural Posture
Commercial Property Dispute / Judgment After Proof Before Answer
Legal Issues
- 1 Whether the defenders were contractually obliged to construct an internal distributor road and roundabout up to the boundary with the Non-Food Retail Site, providing direct access as per the missives and plan.
- 2 Whether the defenders' construction of the road and roundabout short of the boundary constituted full performance of their obligations under the missives.
Ratio Decidendi
The defenders were contractually obliged under the missives to construct the internal distributor road and roundabout up to the boundary with the Non-Food Retail Site, as indicated on the attached plan. The obligation was not satisfied by terminating the road short of the boundary. The Deed of Conditions did not suspend or qualify this obligation, and clause 7 merely provided for further deeds if necessary to give effect to the servitude rights, not for further substantive agreement on road construction.
Court Disposition
Decree granted in favour of the pursuers for declarator and specific implement as per conclusions 1 to 3; decree refused at this stage for conclusion 4, with leave reserved to apply for further orders if necessary.
Orders
- Declarator that the defenders are obliged to construct the road and roundabout up to the boundary with the Non-Food Retail Site as per the missives and plan.
- Declarator that the defenders are in breach of their obligation to obtain necessary consents for construction of the road as required by the missives.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment