Spiersbridge Property Ltd v. Muir Construction [2008] ScotCS CSOH_44 (14 March 2008)
Where a demand has been made on a performance bond in an amount which is ultimately found to exceed the sum due to the party making the demand, that party is obliged to account for that excess to the opposite contracting party (here, the defender), not to the bank. The appropriate implied term is in the building contract, not the bond or banking contract.
- Citation
- [2008] ScotCS CSOH_44
- Parties
- Pursuer: Spiersbridge Property Developments Limited; Defender: Muir Construction Limited
- Jurisdiction
- Scotland
- Judgment Date
- 14 March 2008
- Procedural Posture
- Commercial Building Contract Dispute / Interlocutory Judgment on Legal Issue Before Proof
- Outcome
- Pursuer's plea in law on the bond repayment issue repelled; amendment to counterclaim allowed.
- Legal Topics
- Performance Bonds, Implied Terms, Restitution of Overpayment, Building Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Spiersbridge Property Developments Limited
Pursuer
Muir Construction Limited
Defender
Procedural Posture
Commercial Building Contract Dispute / Interlocutory Judgment on Legal Issue Before Proof
Legal Issues
- 1 Whether, when a performance bond is called and payment made in excess of actual loss, the beneficiary must account for the excess to the bank or to the opposite contracting party
- 2 Whether a term to account for excess must be implied into the building contract, the bond contract, or the banking contract
Ratio Decidendi
Where a demand has been made on a performance bond in an amount which is ultimately found to exceed the sum due to the party making the demand, that party is obliged to account for that excess to the opposite contracting party (here, the defender), not to the bank. The appropriate implied term is in the building contract, not the bond or banking contract.
Court Disposition
Pursuer's plea in law on the bond repayment issue repelled; amendment to counterclaim allowed.
Orders
- Pursuer must account to the defender for any excess received under the performance bond beyond actual loss.
- Minute of Amendment to the Counterclaim allowed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment