Huntaven Properties Ltd v Hunter Construction (Aberdeen) Ltd & Ors [2017] ScotCS CSOH_57 (30 March 2017)
Material loss, injury or damage was evident by September 2009 (surface defects) and certainly by February 2010 (widespread delamination and fibre balling). The pursuer could with reasonable diligence have become aware of the relevant loss by those dates. The existence of the defects liability period and remedial works did not postpone the accrual of the cause of action. Accordingly, the obligations to make reparation had prescribed before the action was raised.
- Citation
- [2017] ScotCS CSOH_57
- Parties
- Pursuer: Huntaven Properties Limited; First Defender: Hunter Construction (Aberdeen) Limited; Second Defender: Airsid Installations Limited; Third Defender: GSLP9999 Limited; Fourth Defender: George Hutchison Associates Limited
- Jurisdiction
- Scotland
- Judgment Date
- 30 March 2017
- Procedural Posture
- Commercial Action (construction Dispute) / Preliminary Proof Before Answer on Prescription
- Outcome
- Claims against the first, third, and fourth defenders are prescribed and dismissed.
- Legal Topics
- Prescription and Limitation of Actions, Breach of Contract, Professional Negligence, Defects Liability, Damages
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Huntaven Properties Limited
Pursuer
Hunter Construction (Aberdeen) Limited
First Defender
Airsid Installations Limited
Second Defender
GSLP9999 Limited
Third Defender
George Hutchison Associates Limited
Fourth Defender
Procedural Posture
Commercial Action (construction Dispute) / Preliminary Proof Before Answer on Prescription
Legal Issues
- 1 Whether the pursuer's claims against the defenders have prescribed under the Prescription (Scotland) Act 1973
- 2 When material loss, injury or damage (damnum) occurred for the purposes of prescription
- 3 Whether the defects liability period or remedial works postponed the accrual of the cause of action
Ratio Decidendi
Material loss, injury or damage was evident by September 2009 (surface defects) and certainly by February 2010 (widespread delamination and fibre balling). The pursuer could with reasonable diligence have become aware of the relevant loss by those dates. The existence of the defects liability period and remedial works did not postpone the accrual of the cause of action. Accordingly, the obligations to make reparation had prescribed before the action was raised.
Court Disposition
Claims against the first, third, and fourth defenders are prescribed and dismissed.
Orders
- Action dismissed against the first, third, and fourth defenders on grounds of prescription.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment