Beechwood Development Company (Scotland) Ltd v Mitchell (t/a Discovery Land Surveys) [2001] ScotCS 30 (12 February 2001)

Beechwood Development Company (Scotland) Ltd v Mitchell (t/a Discovery Land Surveys) [2001] ScotCS 30 (12 February 2001)

Delay in obtaining building warrant was caused by defender's erroneous survey, resulting in a 10-week period of loss for Beechwood, for which damages are awarded based on direct site costs, loss of productivity (overheads/profit), and increased material costs, each quantified and supported by evidence.

Citation
[2001] ScotCS 30
Parties
Pursuer: Beechwood Development Company (Scotland) Limited; Defender: Stuart Mitchell, t/a Discovery Land Surveys
Jurisdiction
Scotland
Judgment Date
12 February 2001
Procedural Posture
Civil / Judgment After Hearing on Evidence
Outcome
Judgment for pursuer
Legal Topics
Professional Negligence, Damages Assessment, Delay in Construction, Breach of Contract

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Beechwood Development Company (Scotland) Limited

Pursuer

Stuart Mitchell, t/a Discovery Land Surveys

Defender

Procedural Posture

Civil / Judgment After Hearing on Evidence

  1. 1 Whether Beechwood sustained loss due to erroneous plotting of Manse Burn by defender
  2. 2 Measure of damages attributable to delay caused by defender's breach

Ratio Decidendi

Delay in obtaining building warrant was caused by defender's erroneous survey, resulting in a 10-week period of loss for Beechwood, for which damages are awarded based on direct site costs, loss of productivity (overheads/profit), and increased material costs, each quantified and supported by evidence.

Court Disposition

Judgment for pursuer

Orders

  • Defender's pleas repelled
  • Pursuer's third plea sustained