CAPITA BUSINESS SERVICES LTDAGAINST THE COMMON SERVICES AGENCY FOR THE SCOTTISH HEALTH SERVICE [2023] ScotCS CSOH_9 (10 February 2023)
The Instructions to Bidders were sufficiently clear that no assumptions were to be included in Final Bids, and that all required costs, including infrastructure build, had to be priced. The pursuer's Final Bid included impermissible assumptions regarding infrastructure build costs, contrary to explicit instructions. The defender's decision to disqualify the pursuer's bid was not disproportionate or irrational and was in accordance with the principles of transparency and equal treatment.
- Citation
- [2023] ScotCS CSOH_9
- Parties
- Pursuer: Capita Business Services Limited; Defender: The Common Services Agency for the Scottish Health Service
- Jurisdiction
- Scotland
- Judgment Date
- 10 February 2023
- Procedural Posture
- Commercial Judicial Review (procurement Challenge) / Opinion Following Preliminary Proof
- Outcome
- Pursuer's challenge refused; defender's disqualification of the pursuer's bid upheld.
- Legal Topics
- Public Contracts, Procurement Procedures, Disqualification of Tenders, Transparency and Equal Treatment, Interpretation of Procurement Documents
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Capita Business Services Limited
Pursuer
The Common Services Agency for the Scottish Health Service
Defender
Procedural Posture
Commercial Judicial Review (procurement Challenge) / Opinion Following Preliminary Proof
Legal Issues
- 1 Whether the defender's Instructions to Bidders were sufficiently clear to permit uniform interpretation by all reasonably well-informed and normally diligent (RWIND) tenderers
- 2 Whether the pursuer's Final Bid was compliant with the Instructions to Bidders
- 3 Whether the defender acted proportionately and rationally in disqualifying the pursuer's bid
Ratio Decidendi
The Instructions to Bidders were sufficiently clear that no assumptions were to be included in Final Bids, and that all required costs, including infrastructure build, had to be priced. The pursuer's Final Bid included impermissible assumptions regarding infrastructure build costs, contrary to explicit instructions. The defender's decision to disqualify the pursuer's bid was not disproportionate or irrational and was in accordance with the principles of transparency and equal treatment.
Court Disposition
Pursuer's challenge refused; defender's disqualification of the pursuer's bid upheld.
Orders
- Declarator refused that the pursuer's Final Bid was compliant.
- Declarator refused that the defender breached obligations under the Public Contracts (Scotland) Regulations 2015.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment