VAN OORD UK LIMITED AGAINST DRAGDOS UK LIMITED 30/09/2020 [2020] ScotCS CSOH_87 (30 September 2020)
The defender was not contractually entitled to omit works and transfer them to other subcontractors except in the specific circumstances provided in clause 14.3 of the NEC3 subcontract, which did not apply. The omission constituted a breach of contract. However, the NEC3 compensation event mechanism applies to such breaches, and the reduction in bill rates for remaining works is a valid contractual consequence under NEC3. The pursuer is not entitled to declarator preventing reduction of rates or payment based on unreduced rates.
- Citation
- [2020] ScotCS CSOH_87
- Parties
- Pursuer: Van Oord UK Limited; Defender: Dragados UK Limited
- Jurisdiction
- Scotland
- Judgment Date
- 30 September 2020
- Procedural Posture
- Commercial Construction Contract Dispute / Debate on Preliminary Pleas to Relevancy
- Outcome
- Declarator refused; breach of contract found but compensation event mechanism applies.
- Legal Topics
- Subcontractor Rights, Variation and Omission of Works, Compensation Events, Interpretation of NEC3 Contracts, Valuation of Change, Breach of Contract, Mutual Trust and Co Operation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Van Oord UK Limited
Pursuer
Dragados UK Limited
Defender
Procedural Posture
Commercial Construction Contract Dispute / Debate on Preliminary Pleas to Relevancy
Legal Issues
- 1 Whether the defender was entitled to omit and transfer works to other subcontractors under the NEC3 subcontract
- 2 Whether the omission and transfer constituted a breach of contract
- 3 Whether the defender was entitled to reduce the bill rate for remaining works after omission
Ratio Decidendi
The defender was not contractually entitled to omit works and transfer them to other subcontractors except in the specific circumstances provided in clause 14.3 of the NEC3 subcontract, which did not apply. The omission constituted a breach of contract. However, the NEC3 compensation event mechanism applies to such breaches, and the reduction in bill rates for remaining works is a valid contractual consequence under NEC3. The pursuer is not entitled to declarator preventing reduction of rates or payment based on unreduced rates.
Court Disposition
Declarator refused; breach of contract found but compensation event mechanism applies.
Orders
- The pursuer's plea for declarator that the defender was not entitled to reduce the bill rate is refused.
- The pursuer's plea for payment based on unreduced bill rates is refused.
Full Case Text
Judgment text and source record