DAVID MACBRAYNE LIMITED AGAINST ATOS IT SERVICES (UK) LIMITED [2018] ScotCS CSOH_32 (05 April 2018)
The defender failed to achieve Milestones 3, 4, 5, and 7 by the revised dates, constituting material breaches of contract. The pursuer was entitled to terminate for cause under clause 55.1.5.2 and 55.1.5.3. The breaches were not caused by authority failures; the primary obligation to supply requirements granularity was on the defender. No valid waiver or personal bar was established. Damages for wasted expenditure on M-0, M-1, and M-2 milestone payments are recoverable. The counterclaim for declarator and damages fails.
- Citation
- [2018] ScotCS CSOH_32
- Parties
- Pursuer: David MacBrayne Limited; Defender: Atos IT Services (UK) Limited
- Jurisdiction
- Scotland
- Judgment Date
- 05 April 2018
- Procedural Posture
- Commercial Action for Breach of Contract and Counterclaim for Declarator and Damages / Proof Before Answer
- Outcome
- Pursuer succeeds; defender's counterclaim dismissed
- Legal Topics
- Termination for Breach, Material Breach, Waiver and Personal Bar, Damages for Wasted Expenditure, Change Control Procedures, Authority Responsibilities, Project Management Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
David MacBrayne Limited
Pursuer
Atos IT Services (UK) Limited
Defender
Procedural Posture
Commercial Action for Breach of Contract and Counterclaim for Declarator and Damages / Proof Before Answer
Legal Issues
- 1 Whether defender failed to achieve contractual milestones and was in material breach
- 2 Whether pursuer was entitled to terminate for cause under contract
- 3 Whether pursuer breached authority responsibilities causing delay
Ratio Decidendi
The defender failed to achieve Milestones 3, 4, 5, and 7 by the revised dates, constituting material breaches of contract. The pursuer was entitled to terminate for cause under clause 55.1.5.2 and 55.1.5.3. The breaches were not caused by authority failures; the primary obligation to supply requirements granularity was on the defender. No valid waiver or personal bar was established. Damages for wasted expenditure on M-0, M-1, and M-2 milestone payments are recoverable. The counterclaim for declarator and damages fails.
Court Disposition
Pursuer succeeds; defender's counterclaim dismissed
Orders
- Pursuer entitled to damages for wasted expenditure on M-0, M-1, and M-2 milestone payments
- Defender's counterclaim for declarator and damages refused
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment