McIntosh Ltd v Balfour Beatty Group Ltd & Anor [2006] ScotCS CSOH_197 (21 December 2006)
The pursuers did not have title to sue at the date of raising the action because there was no valid assignation of the partnership's rights under the Works Contract to the company prior to the action, and subsequent assignation cannot cure this defect. The company acted only as agent for the partnership, not as assignee. There was no clear representation or reliance to found personal bar, and the pursuers, not being parties to the Management Contract, cannot challenge the final certificate under it. The interlocking nature of the contracts does not override the rules of privity of contract.
- Citation
- [2006] ScotCS CSOH_197
- Parties
- Pursuer: Laurence McIntosh Limited; First Defender: Balfour Beatty Group Limited; Second Defender: The Trustees of the National Library of Scotland
- Jurisdiction
- Scotland
- Judgment Date
- 21 December 2006
- Procedural Posture
- Commercial Action (construction Contract Dispute) / Opinion Following Preliminary Proof Before Answer on Title to Sue and Personal Bar
- Outcome
- Pursuers' case on title to sue and personal bar rejected; pursuers lack title to sue and cannot challenge the final certificate.
- Legal Topics
- Title to Sue, Assignation of Contractual Rights, Privity of Contract, Personal Bar (estoppel), Novation, Agency, Reduction of Certificate
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Laurence McIntosh Limited
Pursuer
Balfour Beatty Group Limited
First Defender
The Trustees of the National Library of Scotland
Second Defender
Procedural Posture
Commercial Action (construction Contract Dispute) / Opinion Following Preliminary Proof Before Answer on Title to Sue and Personal Bar
Legal Issues
- 1 Whether the pursuers (company) have title to sue under the Works Contract originally entered into by the partnership
- 2 Whether the pursuers have title to challenge the final certificate issued under the Management Contract
- 3 Whether the second defenders are personally barred from denying the pursuers' title to sue
Ratio Decidendi
The pursuers did not have title to sue at the date of raising the action because there was no valid assignation of the partnership's rights under the Works Contract to the company prior to the action, and subsequent assignation cannot cure this defect. The company acted only as agent for the partnership, not as assignee. There was no clear representation or reliance to found personal bar, and the pursuers, not being parties to the Management Contract, cannot challenge the final certificate under it. The interlocking nature of the contracts does not override the rules of privity of contract.
Court Disposition
Pursuers' case on title to sue and personal bar rejected; pursuers lack title to sue and cannot challenge the final certificate.
Orders
- Pursuers' case dismissed on the preliminary issues of title to sue and personal bar.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment