William Rennie & Co Ltd v BP Exploration Operating Co Ltd [2011] ScotCS CSIH_10 (16 February 2011)
Clause 25 of the Schedule to the Grant of Servitude is to be interpreted commercially, with the 'proposed development' not rigidly defined by the original application but subject to refinement. Compensation is payable where development is prevented solely by the pipeline, unless the respondent proves planning permission would have been refused for reasons unrelated to the pipeline. The planning authority's refusal was solely due to the pipeline, and but for the pipeline, permission would likely have been granted after amendments. The respondents' defence under Clause 25(f) fails as they did not prove refusal would have occurred for other reasons.
- Citation
- [2011] ScotCS CSIH_10
- Parties
- Claimant: William Rennie & Co Ltd; Respondent: BP Exploration Operating Co Ltd
- Jurisdiction
- Scotland
- Judgment Date
- 16 February 2011
- Procedural Posture
- Stated Case Under Section 3 of the Administration of Justice (scotland) Act 1972 / Appeal From Arbitration; Opinion of the Court
- Outcome
- Appeal allowed; questions 1-4 answered in the affirmative, question 5 not arising or answered affirmatively.
- Legal Topics
- Servitude, Compensation for Prevention of Development, Interpretation of Commercial Contracts, Planning Permission, Contra Proferentem Rule
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
William Rennie & Co Ltd
Claimant
BP Exploration Operating Co Ltd
Respondent
Procedural Posture
Stated Case Under Section 3 of the Administration of Justice (scotland) Act 1972 / Appeal From Arbitration; Opinion of the Court
Legal Issues
- 1 Interpretation of Clause 25 of Schedule to Grant of Servitude
- 2 Whether compensation is payable for prevention of development by pipeline
- 3 Application of Clause 25(f) as defence to compensation claim
Ratio Decidendi
Clause 25 of the Schedule to the Grant of Servitude is to be interpreted commercially, with the 'proposed development' not rigidly defined by the original application but subject to refinement. Compensation is payable where development is prevented solely by the pipeline, unless the respondent proves planning permission would have been refused for reasons unrelated to the pipeline. The planning authority's refusal was solely due to the pipeline, and but for the pipeline, permission would likely have been granted after amendments. The respondents' defence under Clause 25(f) fails as they did not prove refusal would have occurred for other reasons.
Court Disposition
Appeal allowed; questions 1-4 answered in the affirmative, question 5 not arising or answered affirmatively.
Orders
- Respondents liable to pay compensation to claimants under Clause 25 of Schedule to Grant of Servitude.
- Matter remitted to arbiter for determination of quantum.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment