WEATHERFORD SWITZERLAND TRADING AND DEVELOPMENT GmbH AGAINST iiiTEC LTD [2019] ScotSC SC_87 (05 November 2019)

WEATHERFORD SWITZERLAND TRADING AND DEVELOPMENT GmbH AGAINST iiiTEC LTD [2019] ScotSC SC_87 (05 November 2019)

The court found that the defender was liable for the sums claimed as the contractual obligations were clear and no valid defence was established.

Citation
[2019] ScotSC SC_87
Parties
Pursuer: Weatherford Switzerland Trading and Development GmbH; Defender: iiiTEC Ltd
Jurisdiction
Scotland
Judgment Date
05 November 2019
Procedural Posture
Commercial Claim / Judgment
Outcome
decree for payment granted
Legal Topics
Breach of Contract, Payment of Sums Due

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Weatherford Switzerland Trading and Development GmbH

Pursuer

iiiTEC Ltd

Defender

Procedural Posture

Commercial Claim / Judgment

  1. 1 Whether the defender is liable to pay the sums claimed under the contract
  2. 2 Whether the pursuer is entitled to decree for payment

Ratio Decidendi

The court found that the defender was liable for the sums claimed as the contractual obligations were clear and no valid defence was established.

Court Disposition

decree for payment granted

Orders

  • Defender to pay the sums claimed to the pursuer