Fordell Estates Ltd v Deloitte LLP [2014] ScotCS CSOH_55 (21 March 2014)
No binding contract was concluded as the parties did not manifest an intention to be immediately bound; the requirement for evidence of works being carried out remained unmet and was not waived.
- Citation
- [2014] ScotCS CSOH_55
- Parties
- Pursuer: Fordell Estates Limited; Defender: Deloitte LLP
- Jurisdiction
- Scotland
- Judgment Date
- 21 March 2014
- Procedural Posture
- Civil / Judgment
- Outcome
- claim refused
- Legal Topics
- Formation of Contract, Dilapidations, Settlement Agreements
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Full judgment text Downloadable case file Legal principles 1 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Parties
Fordell Estates Limited
Pursuer
Deloitte LLP
Defender
Procedural Posture
Civil / Judgment
Legal Issues
- 1 Whether a binding settlement agreement was concluded between the parties regarding dilapidations claim
- 2 Whether the requirement for evidence of works being carried out was a condition precedent to settlement
Ratio Decidendi
No binding contract was concluded as the parties did not manifest an intention to be immediately bound; the requirement for evidence of works being carried out remained unmet and was not waived.
Court Disposition
claim refused
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment