Benoiton Construction (Pty) Ltd v Muller (CC 04/2017) [2020] SCSC 450 (17 February 2020)

Benoiton Construction (Pty) Ltd v Muller (CC 04/2017) [2020] SCSC 450 (17 February 2020)

The Court found that a contract existed based on documentary evidence and conduct, the Defendant breached the contract by failing to pay for works done, and the Plaintiff was entitled to the claimed sum, VAT, interest, and costs.

Citation
[2020] SCSC 450
Parties
Plaintiff: Benoiton Construction (Pty) Ltd; Defendant: Arnoud Muller
Court
Supreme Court
Jurisdiction
Seychelles
Judgment Date
17 February 2020
Case Number
CC 04/2017
Procedural Posture
Civil / Judgment After Ex Parte Hearing
Outcome
Judgment for the Plaintiff
Legal Topics
Construction Contracts, Oral Contracts, Agency, Breach of Contract, Damages, Admissibility of Evidence
Source Language
English

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Benoiton Construction (Pty) Ltd

Plaintiff

Arnoud Muller

Defendant

Procedural Posture

Civil / Judgment After Ex Parte Hearing

  1. 1 Whether a valid contract existed between the parties despite lack of written agreement
  2. 2 Whether the Defendant breached the contract by failing to pay for construction works
  3. 3 Whether oral and documentary evidence is admissible to prove the contract under Article 1341 of the Civil Code of Seychelles

Ratio Decidendi

The Court found that a contract existed based on documentary evidence and conduct, the Defendant breached the contract by failing to pay for works done, and the Plaintiff was entitled to the claimed sum, VAT, interest, and costs.

Court Disposition

Judgment for the Plaintiff

Orders

  • Defendant to pay Plaintiff US$127,664.14 (US$87,210.59 for works done and US$40,453.55 for VAT) with interest and costs