Naidoo v Innocent Alpha Vintigadoo & Anor (161 of 2019) [2023] SCSC 212 (30 January 2023)

Naidoo v Innocent Alpha Vintigadoo & Anor (161 of 2019) [2023] SCSC 212 (30 January 2023)

The defendants committed a serious and substantial breach of contract by failing to construct the building in accordance with approved plans and legal requirements, specifically by building too close to the boundary line, which would have rendered the construction unlawful and subject to demolition. This breach...

Source-derived case information.

Citation
[2023] SCSC 212
Parties
Plaintiff: Bernadette Naidoo; 1st Defendant: Innocente Alpha Vintigadoo; 2nd Defendant: Abdul Kalam Azad
Court
Supreme Court
Jurisdiction
Seychelles
Case Number
161 of 2019
Procedural Posture
Civil Suit / Judgment
Outcome
Plaint partially allowed; contract rescinded for substantial breach; refund of advance payment ordered; claim for moral damages dismissed; costs and interest awarded to plaintiff.
Legal Topics
Rescission of Contract, Breach of Contract, Damages, Advance Payment, Construction Standards
Source Language
en
Contract Law Construction Law Rescission of Contract Breach of Contract Damages Advance Payment Construction Standards

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 11 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Bernadette Naidoo

Plaintiff

Innocente Alpha Vintigadoo

1st Defendant

Abdul Kalam Azad

2nd Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the defendants breached the construction contract by failing to comply with approved plans and legal requirements
  2. 2 Whether the plaintiff is entitled to rescission of the contract and refund of advance payment
  3. 3 Whether the plaintiff is entitled to moral damages for inconvenience and stress

Ratio Decidendi

The defendants committed a serious and substantial breach of contract by failing to construct the building in accordance with approved plans and legal requirements, specifically by building too close to the boundary line, which would have rendered the construction unlawful and subject to demolition. This breach justified rescission of the contract and refund of the advance payment to the plaintiff. The defendants were not entitled to retain any part of the advance payment as their performance was minimal and worthless to the plaintiff. The claim for moral damages was dismissed for lack of proof.

Court Disposition

Plaint partially allowed; contract rescinded for substantial breach; refund of advance payment ordered; claim for moral damages dismissed; costs and interest awarded to plaintiff.

Orders

  • The agreement of 10 April 2019 is rescinded for substantial breach.
  • Defendants to refund the plaintiff SR 265,800.00.