Camille v Vandagne Plant Hire Company (Pty) Ltd (CS 29/2008) [2012] SCSC 56 (2 December 2012)

Camille v Vandagne Plant Hire Company (Pty) Ltd (CS 29/2008) [2012] SCSC 56 (2 December 2012)

The defendant breached the contract by failing to construct the driveway in accordance with the approved plan and gradient, resulting in a defective and unusable driveway. However, the plaintiff's engineer's omission to properly supervise the work contributed to the defect. The court apportioned liability, holding...

Source-derived case information.

Citation
[2012] SCSC 56
Parties
Plaintiff: Camille; Defendant: Vandagne Plant Hire Company (Pty) Ltd
Court
Supreme Court
Jurisdiction
Seychelles
Case Number
CS 29/2008
Procedural Posture
Civil / Judgment
Outcome
judgment for the plaintiff in part
Legal Topics
Breach of Contract, Damages, Contributory Negligence, Construction Contracts
Source Language
en
Contract Law Civil Procedure Breach of Contract Damages Contributory Negligence Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 7 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Camille

Plaintiff

Vandagne Plant Hire Company (Pty) Ltd

Defendant

Procedural Posture

Civil / Judgment

  1. 1 Whether the defendant breached the contract by failing to construct the driveway as per the approved plan
  2. 2 Whether the driveway was defective and unusable as a result of the defendant's actions
  3. 3 Whether there was contributory negligence or fault by the plaintiff's engineer affecting the quantum of damages

Ratio Decidendi

The defendant breached the contract by failing to construct the driveway in accordance with the approved plan and gradient, resulting in a defective and unusable driveway. However, the plaintiff's engineer's omission to properly supervise the work contributed to the defect. The court apportioned liability, holding the defendant responsible for 80% of the damages and the plaintiff for 20%.

Court Disposition

judgment for the plaintiff in part

Orders

  • Defendant to pay the plaintiff R72,000 as damages
  • Defendant to pay costs of the action