The court found that granting the injunction would cause more harm than refusing it, as the contract between the parties ended on the day of the ruling and the 1st Respondent would be left without security. Damages were deemed an adequate remedy for the applicant.

Source-derived case information.

Citation
[2021] SCSC 311
Parties
Petitioner: Marpol Security Pty Ltd; 1st Respondent: Seychelles Heritage Foundation; 2nd Respondent: Government of Seychelles Procurement Oversight Unit
Court
Supreme Court
Jurisdiction
Seychelles
Case Number
MA 119 of 2021 (arising in CS 48/2021)
Procedural Posture
Interim Injunction Application / Ruling on Ex Parte Interim Injunction Motion
Outcome
Application refused
Legal Topics
Interim Injunctions, Tender Process, Discretionary Relief
Source Language
en
Administrative Law Public Procurement Interim Injunctions Tender Process Discretionary Relief

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Marpol Security Pty Ltd

Petitioner

Seychelles Heritage Foundation

1st Respondent

Government of Seychelles Procurement Oversight Unit

2nd Respondent

Procedural Posture

Interim Injunction Application / Ruling on Ex Parte Interim Injunction Motion

  1. 1 Whether the applicant is entitled to an interim injunction restraining the tender process
  2. 2 Whether damages are an adequate remedy for exclusion from the tender process

Ratio Decidendi

The court found that granting the injunction would cause more harm than refusing it, as the contract between the parties ended on the day of the ruling and the 1st Respondent would be left without security. Damages were deemed an adequate remedy for the applicant.

Court Disposition

Application refused

Orders

  • Motion for interim injunction dismissed