Benoit vs Interior and Construction Design (Pty) Ltd & another (CS 146.2012) [2013] SCSC 77 (24 October 2013)
- Citation
- [2013] SCSC 77
- Status
- Judgment
- Jurisdiction
- Seychelles
- Court
- Supreme Court
- Posture
- Civil / Judgment
- Case number
- CS 146.2012
- Language
- English
More details
- Court
- Supreme Court
- Posture
- Civil / Judgment
- Case number
- CS 146.2012
- Language
- English
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The plaintiff unilaterally and unlawfully breached the building contract, leaving a balance of Rs.624,355 due to the first defendant, who is entitled to judgment for that sum with interest at the legal rate.
Court disposition
Plaintiff's claim dismissed; judgment for first defendant on counterclaim.
Orders
- Plaintiff's claim dismissed in entirety
- Judgment for first defendant in sum of Rs.624,355 with interest at 4% per annum from date of plaint
- Plaintiff to pay costs
02
Material facts
Parties
Michel Benoit
Plaintiff Counsel: Mr. C. LucasInterior and Construction Design (Pty) Ltd
First Defendant Counsel: Mr. A. DerjacquesSarah Sabadin
Second Defendant Counsel: Mr. A. DerjacquesAmounts and remedies
- Plaintiff's Claim: SCR 792,338.88
- Defendants' Counterclaim: SCR 1,092,967
- Judgment Sum Awarded to First Defendant: SCR 624,355
- Interest Rate Awarded: 4
03
Procedural history
Posture
Civil / Judgment
04
Questions and positions
Legal issues
- 01
Whether the plaintiff breached the building contract
- 02
Whether the defendants are entitled to the counterclaim amount
- 03
Whether interest at commercial rate is payable
Party arguments
- Applicant
- Plaintiff alleged defendants breached the contract and claimed damages of Rs.792,338.88.
- Respondent
- Defendants denied breach, claimed plaintiff breached contract, and counterclaimed for Rs.1,092,967 with interest, including Rs.115,000 for access road.
05
Court’s reasoning
Legal principles
- 01
General contract law
A party who unilaterally and unlawfully breaches a contract is liable for resulting losses.
- 02
General contract law
Interest is payable at the legal rate in absence of agreement to a higher rate.
06
Ratio, limits and disposition
Ratio decidendi
The plaintiff unilaterally and unlawfully breached the building contract, leaving a balance of Rs.624,355 due to the first defendant, who is entitled to judgment for that sum with interest at the legal rate.
Obiter and limits
- Plaintiff failed to appear and prosecute the claim despite adjournments.
- No agreement existed as to commercial interest rate; only legal rate applies.
Court disposition
Plaintiff's claim dismissed; judgment for first defendant on counterclaim.
- Plaintiff's claim dismissed in entirety
- Judgment for first defendant in sum of Rs.624,355 with interest at 4% per annum from date of plaint
- Plaintiff to pay costs
Source and reliance status
Supreme Court
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
Supreme Court
Judgment
IN THE SUPREME COURT OF SEYCHELLES Civil Side: CS 146/2007 [2013] SCSC 77
MICHEL BENOIT Plaintiff versus INTERIOR AND CONSTRUCTION DESIGN (PTY) LTD First DefendantSARAH SABADIN Second Defendant Heard: Counsel: 24 October 2013 Mr. C. Lucas for plaintiff Mr. A. Derjacques for defendants Delivered: 24 October 2013
JUDGMENT Karunakaran J I believe I need not write a detailed judgment in this matter. The facts are simple, clear and straight forward. This is an action of breach of contract. At all the material times the Plaintiff was the owner of a plot of land situated at Sorento, Glacis, Mahe. The first Defendant is a company registered in Seychelles engaged in the business of construction, whereas the second Defendant Sarah Sabadin is one of its directors. Admittedly, on the 27th of January 2006 the Plaintiff and the first Defendant entered into a contract for the construction of a dwelling house as per Exhibit P1. Subsequently, the Plaintiff by a plaint dated the 9th May 2007 came before this Court alleging that the Defendants were in breach of contract, as a result of the said breach he suffered loss and damages in the total sum of Rs.792,338.88/-. Hence he claimed the said sum jointly and severely against the Defendants. The Defendants on the other hand in their defence completely denied the Plaintiff’s claim and also made a counterclaim against the Plaintiff in the sum of Rs.1,092,967/- with interest at the commercial rate of 7.5% per annum inclusive of the sum Rs.115,000/- due for construction of the access road. The Plaintiff denied the counterclaim made by the Defendants. The facts as transpired from the evidence are thus:- A building contract was entered into on the 27th January
2006 between the Plaintiff and the first Defendant namely, Interior and Construction Design Pty Ltd. This was for the construction of a dwelling house at Sorento, Glacis on parcel H3451 for an agreed contract sum of Rs.1,795,145/-. In fact the contract did not include the construction of an access road to the actual site. However, due to the topography of the site it was impossible to access the steep terrain in order to carry out the construction work. Hence, the Defendants had to put up an access road to complete the main building. The contract in fact stipulated the building of the dwelling house should be completed over a period of approximately 12 months but no commencement date was set or confirmed. According to the Defendants although the building contract contemplated the instalment payments the first payment that is the down payment should be made at the commence date, the Plaintiff did not pay the agreed sum in full. Moreover, the second Defendant testified that although the original contract was for the construction of a dwelling house without giving due notice to the Defendant company the Plaintiff changed the dwelling house into a commercial tourism related premises. As a result the Defendants suffered inconvenience, hardship and had to change the original project from dwelling to commercial building. According to the Defendant, the Plaintiff unilaterally and
unlawfully breached the said building contract with the first Defendant. Moreover, it is the case of the Defendant that the value of the works effected amount to the sum of Rs.1,099,355/- of which the Plaintiff has paid only Rs.475,000/-. Therefore, according to the Defendant the Plaintiff is liable to the first Defendant to pay the balance in the sum of Rs.624,355/-. In the circumstances, the Defendants move for a judgment against the Plaintiff in the said sum with interest at the commercial rate of 7.5% per annum in this matter. Before I consider the case on the merits I wish to mention that the Plaintiff despite repeated adjournments failed to appear in Court to give evidence in this matter. In fact, the last time the case had been set for hearing the Plaintiff’s counsel moved for an adjournment stating that the Plaintiff was overseas, and the Court granted the adjournment on condition that it should be the last chance for the Plaintiff to be present in Court and proceed with the case. However again the Plaintiff defaulted, at the same time the Plaintiff’s counsel informed the Court that the Plaintiff is not longer interested to prosecute the claim and therefore moved the Court to withdraw the claim of the Plaintiff. The Court accordingly granted leave and the Plaintiff’s claim was set aside. Whereas the counsel for the Defendants, Mr. Derjacques, moved the Court to proceed
to hear the counterclaim of the Defendant and give judgment for the Plaintiff. Having considered the entire evidence on record, I am of the view that the Defendants have established the following facts to the required degree in civil law:- (i) The Plaintiff unilaterally and unlawfully breached the building contract between the parties dated the 27th January 2006; (ii) The value of the total work carried out by the Defendants on the Plaintiff’s property amounts to the sum of Rs.1,099,355/-; (iii) The Plaintiff has so far paid only Rs.475,000/-, leaving a balance of Rs.624,355/- due and payable to the Defendants; (iv) Despite repeated request the Plaintiff has failed to pay the said sum to the Defendants. In view of all the above I am satisfied that the Defendants have established their counterclaim to the extent of only Rs.624,355/- against the Plaintiff. On the issue of commercial rate of interest at 7.5%, since there is no agreement between the parties as to the rate of interest at the time of entering into the contract I am reluctant to award the rate of interest at 7.5%. Whereas I find the Defendants are entitled to claim interest only at 4%, the legal rate as from the date of the plaint. In the circumstances, I hereby enter judgment for the First Defendant in the sum of Rs.624,355/- with interest on the said sum at 4% per annum as from the date of plaint and with cost. For the avoidance of doubt I hereby confirm that the Plaintiff’s claim is dismissed in its entirety. Judgment entered accordingly for the Defendants. Signed, dated and delivered at Ile du Port on D Karunakaran Judge of the Supreme Court 4
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.