Bristol v Rosenbauer (SCA 71 of 2018) [2021] SCCA 54 (7 September 2021)

Bristol v Rosenbauer (SCA 71 of 2018) [2021] SCCA 54 (7 September 2021)

The appellant breached the building contract by delivering defective and incomplete work and abandoning the site; the respondent proved her claim for damages except for the sum relating to roof repairs, which was adjusted based on evidence; the appellant's counterclaim failed due to lack of reliable supporting...

Source-derived case information.

Citation
[2021] SCCA 54
Parties
Appellant: Mr. Andre Bristol; Respondent: Dr. Ellen Astrid Corina Rosenbauer
Court
Court of Appeal
Jurisdiction
Seychelles
Case Number
SCA 71 of 2018
Procedural Posture
Civil Appeal / Judgment on Appeal
Outcome
Appeal dismissed except for partial success on Ground 1; damages adjusted.
Legal Topics
Breach of Building Contract, Damages, Counterclaim, Assessment of Evidence
Source Language
en
Contract Law Breach of Building Contract Damages Counterclaim Assessment of Evidence

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 4 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Mr. Andre Bristol

Appellant

Dr. Ellen Astrid Corina Rosenbauer

Respondent

Procedural Posture

Civil Appeal / Judgment on Appeal

  1. 1 Whether the appellant breached the building contract and is liable for damages
  2. 2 Whether the respondent proved her claim for damages
  3. 3 Whether the appellant's counterclaim was substantiated

Ratio Decidendi

The appellant breached the building contract by delivering defective and incomplete work and abandoning the site; the respondent proved her claim for damages except for the sum relating to roof repairs, which was adjusted based on evidence; the appellant's counterclaim failed due to lack of reliable supporting evidence; the trial judge's assessment of evidence and damages was largely correct except for the roof repair sum, which was corrected on appeal.

Court Disposition

Appeal dismissed except for partial success on Ground 1; damages adjusted.

Orders

  • Respondent awarded damages for breach of contract in the sum of SR 448,560.75 with interest at the commercial rate from the date of filing the plaint.
  • Costs for the appeal awarded to the respondent.