Seychelles Savings Bank v Tive (349 of 2008) [2009] SCSC 65 (9 December 2009)

Seychelles Savings Bank v Tive (349 of 2008) [2009] SCSC 65 (9 December 2009)

The Defendant is liable for the outstanding loan balance and interest at the original agreed rate of 10% per annum, as the Plaintiff failed to notify the Defendant of any increase in interest rate. The Plaintiff's delay and lack of communication preclude recovery of penal interest above the agreed rate. Judgment is...

Source-derived case information.

Citation
[2009] SCSC 65
Parties
Plaintiff: Seychelles Savings Bank; Defendant: Travis Chang Pen Tive
Court
Supreme Court
Jurisdiction
Seychelles
Case Number
349 of 2008
Procedural Posture
Civil / Judgment
Outcome
Judgment for Plaintiff in part
Legal Topics
Loan Agreement, Interest Variation, Security for Debt, Delay in Enforcement, Notice Requirements
Source Language
en
Contract Law Banking Law Loan Agreement Interest Variation Security for Debt Delay in Enforcement Notice Requirements

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 12
Sign in to unlock

Parties

Seychelles Savings Bank

Plaintiff

Travis Chang Pen Tive

Defendant

Procedural Posture

Civil / Judgment

  1. 1 Whether the Defendant is liable for the outstanding loan balance and interest as claimed by the Plaintiff
  2. 2 Whether the Plaintiff was entitled to unilaterally increase the interest rate without notifying the Defendant
  3. 3 Whether the Plaintiff's delay and lack of communication affected the Defendant's liability

Ratio Decidendi

The Defendant is liable for the outstanding loan balance and interest at the original agreed rate of 10% per annum, as the Plaintiff failed to notify the Defendant of any increase in interest rate. The Plaintiff's delay and lack of communication preclude recovery of penal interest above the agreed rate. Judgment is entered for the Plaintiff for the net unpaid balance as at 27th June 2007, with interest at 10% per annum from that date, plus specified charges and taxed costs.

Court Disposition

Judgment for Plaintiff in part

Orders

  • Defendant to pay Plaintiff SR85,341.39 with interest at 10% per annum from 27th June 2007
  • Defendant to pay charges of SR350.00