Sunshine Properties Pty Ltd v Fada Construction Company Pty Ltd (CC66/2015) [2020] SCSC 410 (8 January 2020)

Sunshine Properties Pty Ltd v Fada Construction Company Pty Ltd (CC66/2015) [2020] SCSC 410 (8 January 2020)

The Plaintiff failed to particularise the alleged defects, did not provide the contractual schedules of conditions, and did not prove that remedial costs related to the perimeter fence. There was no completion date in the agreement to support a claim for liquidated damages. The Plaintiff did not establish breach of...

Source-derived case information.

Citation
[2020] SCSC 410
Parties
Plaintiff: Sunshine Properties Pty Limited; Defendant: Fada Construction Company Pty Ltd
Court
Supreme Court
Jurisdiction
Seychelles
Case Number
CC66/2015
Procedural Posture
Civil / Judgment
Outcome
Plaint dismissed with costs to the Defendant.
Legal Topics
Breach of Contract, Damages, Construction Contracts, Burden of Proof
Source Language
en
Contract Law Civil Procedure Breach of Contract Damages Construction Contracts Burden of Proof

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Sunshine Properties Pty Limited

Plaintiff

Fada Construction Company Pty Ltd

Defendant

Procedural Posture

Civil / Judgment

  1. 1 Whether the Defendant breached the construction agreement by delivering defective work and failing to comply with specifications
  2. 2 Whether the Plaintiff is entitled to damages for breach, liquidated damages for delay, and remedial costs

Ratio Decidendi

The Plaintiff failed to particularise the alleged defects, did not provide the contractual schedules of conditions, and did not prove that remedial costs related to the perimeter fence. There was no completion date in the agreement to support a claim for liquidated damages. The Plaintiff did not establish breach of contract or entitlement to damages on a balance of probabilities.

Court Disposition

Plaint dismissed with costs to the Defendant.

Orders

  • The Plaint is dismissed with costs.