Vijay Construction (Pty) Ltd v Andre (MC 108/2014) [2016] SCSC 21 (25 January 2016)

Vijay Construction (Pty) Ltd v Andre (MC 108/2014) [2016] SCSC 21 (25 January 2016)

The respondent acted unfairly and in breach of its duty of procedural fairness by failing to make a decision on the suspension order for over twenty-three months, despite the suspension being described as temporary. The petitioner was not accorded a fair hearing or timely resolution, entitling the petitioner to...

Source-derived case information.

Citation
[2016] SCSC 21
Parties
Petitioner: Vijay Construction (Proprietary) Limited; Respondent: Patrick Andre, Principal Secretary, Department of Transport, Ministry of Home Affairs and Transport
Court
Supreme Court
Jurisdiction
Seychelles
Case Number
MC 108/2014
Procedural Posture
Judicial Review / Judgment
Outcome
Petition allowed
Legal Topics
Judicial Review, Procedural Fairness, Suspension of Administrative Approval, Natural Justice
Source Language
en
Administrative Law Judicial Review Procedural Fairness Suspension of Administrative Approval Natural Justice

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Vijay Construction (Proprietary) Limited

Petitioner

Patrick Andre, Principal Secretary, Department of Transport, Ministry of Home Affairs and Transport

Respondent

Procedural Posture

Judicial Review / Judgment

  1. 1 Whether the suspension of approval for use of buses by the petitioner was lawful, reasonable, and procedurally fair
  2. 2 Whether the respondent failed in its duty of procedural fairness by not making a timely decision

Ratio Decidendi

The respondent acted unfairly and in breach of its duty of procedural fairness by failing to make a decision on the suspension order for over twenty-three months, despite the suspension being described as temporary. The petitioner was not accorded a fair hearing or timely resolution, entitling the petitioner to judicial review and relief.

Court Disposition

Petition allowed

Orders

  • Writ of Certiorari quashing the suspension order dated 6th February 2014
  • Writ of Mandamus ordering the respondent to revoke, with immediate effect, the suspension order imposed on 6th February 2014 in relation to the use by the petitioner of three buses for transportation of employees