PPG Industries (Singapore) Pte Ltd v Compact Metal Industries Ltd
The Court held that the defendant was not liable for the full 273 days of additional site preliminaries because 87 days of the delay (78 days for stop work orders and 9 days for exceptionally adverse weather) were caused by events not attributable to the defendant; damages were therefore reduced from $1,040,662.35 (273 days) to $709,022.70 (186 days). The Court also held that the respondent’s claim for liquidated damages was recoverable under the first limb of Hadley as ordinary and foreseeable loss imputed to the defendant given the construction industry context, and remitted the defendant’s counterclaim to the Judge below for determination because the GD did not disclose reasoning on...
- Citation
- [2013] SGCA 23
- Parties
- Appellant (original Defendant): Compact Metal Industries Ltd; Respondent (original Plaintiff): PPG Industries (Singapore) Pte Ltd
- Court
- Court of Appeal
- Jurisdiction
- Singapore
- Judgment Date
- 14 March 2013
- Case Number
- Civil Appeal No 125 of 2011
- Procedural Posture
- Civil Appeal / Court of Appeal Decision on Appeal From the High Court
- Outcome
- Appeal allowed in part; High Court decision otherwise affirmed; counterclaim remitted to trial judge
- Legal Topics
- Causation of Delay, Concurrent Delays and Apportionment, Liquidated Damages, Remoteness of Damage (hadley V Baxendale), Expert Evidence Weight, Separate Legal Personality and Attribution
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Compact Metal Industries Ltd
Appellant (original Defendant)
PPG Industries (Singapore) Pte Ltd
Respondent (original Plaintiff)
Procedural Posture
Civil Appeal / Court of Appeal Decision on Appeal From the High Court
Legal Issues
- 1 Whether the defendant’s breach caused 273 days of delay or whether parts were caused by other delaying events
- 2 Whether damages for additional site preliminaries should be reduced to reflect concurrent delays
- 3 Whether the plaintiff could recover liquidated damages it paid to the main contractor and whether such loss was too remote
Ratio Decidendi
The Court held that the defendant was not liable for the full 273 days of additional site preliminaries because 87 days of the delay (78 days for stop work orders and 9 days for exceptionally adverse weather) were caused by events not attributable to the defendant; damages were therefore reduced from $1,040,662.35 (273 days) to $709,022.70 (186 days). The Court also held that the respondent’s claim for liquidated damages was recoverable under the first limb of Hadley as ordinary and foreseeable loss imputed to the defendant given the construction industry context, and remitted the defendant’s counterclaim to the Judge below for determination because the GD did not disclose reasoning on...
Court Disposition
Appeal allowed in part; High Court decision otherwise affirmed; counterclaim remitted to trial judge
Orders
- Reduce damages for additional site preliminaries from $1,040,662.35 to $709,022.70
- Remit the defendant’s counterclaim to the Judge below for decision and reasons
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment