DMC v DMD
Court held that (1) no contractual express requirement in Section 2 cl 24 prevented DMC from imposing backcharges and, on the facts, DMD had sufficient notice of DMC stepping in; (2) DMD elected to waive SOPA s26 suspension by continuing to perform and claiming for works, so s 26 could not be relied on as a defence...
Source-derived case information.
- Citation
- [2025] SGHC 151
- Parties
- Claimant: DMC; Defendant: DMD; Claimant in Counterclaim: DMD; Defendant in Counterclaim: DMC
- Court
- General Division of the High Court
- Jurisdiction
- Singapore
- Judgment Date
- 6 August 2025
- Case Number
- HC/OC 868/2023
- Procedural Posture
- Originating Claim for Breach of Subcontract and Counterclaim Under Sub Contracts (road Marking) / Final Judgment (general Division of the High Court)
- Outcome
- Claim allowed in part in favour of DMC; DMD's counterclaim dismissed
- Legal Topics
- Backcharges, Liquidated Damages, Waiver by Election, SOPA S26 Suspension, Contract Interpretation, Pre Judgment Interest, Unjust Enrichment, Estoppel
- Source Language
- english
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
DMC
Claimant
DMD
Defendant
DMD
Claimant in Counterclaim
DMC
Defendant in Counterclaim
Procedural Posture
Originating Claim for Breach of Subcontract and Counterclaim Under Sub Contracts (road Marking) / Final Judgment (general Division of the High Court)
Legal Issues
- 1 Whether specific notice was required before general contractor could incur backcharges (Section 2 cl 24 / general damages)
- 2 Scope and effect of agreements recorded in 14 June 2022 minutes (application and meaning of "3rd party")
- 3 Entitlement to items claimed in Backcharge 1 (site expenses, depreciation, dormitory/ancillary costs)
Ratio Decidendi
Court held that (1) no contractual express requirement in Section 2 cl 24 prevented DMC from imposing backcharges and, on the facts, DMD had sufficient notice of DMC stepping in; (2) DMD elected to waive SOPA s26 suspension by continuing to perform and claiming for works, so s 26 could not be relied on as a defence to Backcharge 3; (3) disputed site and ancillary expenses and depreciation claimed by DMC were reasonable and recoverable; (4) Backcharge 2 was not proven excessive; (5) personnel obligations in Section 2 (cll 8.1, 8.4.1) applied to DMD; (6) liquidated damages clause was a genuine pre-estimate and LD for delays (including unfinished Fifth Month Field Tests) was payable; and (7)...
Court Disposition
Claim allowed in part in favour of DMC; DMD's counterclaim dismissed
Orders
- DMC's claims for Backcharges 1 to 6 allowed
- DMC's claim for liquidated damages in the sum of 888300.00 SGD (excluding GST) allowed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment