RANGE CONSTRUCTION PTE LTD v GOLDBELL ENGINEERING PTE LTD

RANGE CONSTRUCTION PTE LTD v GOLDBELL ENGINEERING PTE LTD

The application to set aside part of the adjudication determination was dismissed. The adjudicator acted within the SOP Act jurisdiction in considering liquidated damages when those were raised in the payment response; he was not required to identify the exact completion date but could identify a reasonable date (17...

Source-derived case information.

Citation
[2020] SGHC 191
Parties
Applicant: Range Construction Pte Ltd; Respondent: Goldbell Engineering Pte Ltd
Court
General Division of the High Court
Jurisdiction
Singapore
Judgment Date
10 September 2020
Case Number
HC/OS 382/2020
Procedural Posture
Originating Summons Under Section 27(5) of the Building and Construction Industry Security of Payment Act (cap 30 B) / Judgment on Application to Set Aside Adjudication Determination (grounds of Decision)
Outcome
Application dismissed
Legal Topics
Setting Aside Adjudication Determination, Liquidated Damages, Retention Sums and Handing Over Certificate, Natural Justice / Fair Hearing, Interpretation of Contractual Clauses (clauses 19.1 and 19.2), Set Off for Prior Payments
Source Language
english
Building and Construction Law Adjudication Contract Law Administrative Law Setting Aside Adjudication Determination Liquidated Damages Retention Sums and Handing Over Certificate Natural Justice / Fair Hearing +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Range Construction Pte Ltd

Applicant

Goldbell Engineering Pte Ltd

Respondent

Procedural Posture

Originating Summons Under Section 27(5) of the Building and Construction Industry Security of Payment Act (cap 30 B) / Judgment on Application to Set Aside Adjudication Determination (grounds of Decision)

  1. 1 Whether an adjudicator under the SOP Act has jurisdiction to consider or award liquidated damages
  2. 2 Whether the adjudicator exceeded jurisdiction by identifying or effectively designating a completion date
  3. 3 Whether there were breaches of the fair hearing rule (natural justice) in the adjudication process

Ratio Decidendi

The application to set aside part of the adjudication determination was dismissed. The adjudicator acted within the SOP Act jurisdiction in considering liquidated damages when those were raised in the payment response; he was not required to identify the exact completion date but could identify a reasonable date (17 November 2018) as a minimum period for which liquidated damages were payable; there was no breach of the fair hearing rule nor a failure to consider material matters sufficient to set aside the determination; prior payments set out in the payment response could be relied upon and set off against variation claims.

Court Disposition

Application dismissed

Orders

  • Application to set aside part of the adjudication determination dismissed
  • Costs awarded to respondent Goldbell Engineering Pte Ltd fixed at SGD 8,000 all-in