Resource Piling Pte Ltd v Geocon Piling & Engineering Pte Ltd and Another

Resource Piling Pte Ltd v Geocon Piling & Engineering Pte Ltd and Another

The letter of award incorporated Resource's tender conditions and expressly required re-measurement by actual quantities, so payment was to be on actual pile lengths; Geocon breached by failing to secure the crane-use protection and by not ensuring unobstructed site access, causing delay and additional crane rental...

Source-derived case information.

Citation
[2006] SGHC 134
Parties
Plaintiff: Resource Piling Pte Ltd; Defendant: Geocon Piling & Engineering Pte Ltd; Defendant / Related Party: Multi-Con Systems Pte Ltd
Court
General Division of the High Court
Jurisdiction
Singapore
Judgment Date
26 July 2006
Case Number
Suit 334/2004, 282/2004
Procedural Posture
Civil: Contract (construction/subcontract) / Assessment of Damages After Liability Determined at Trial
Outcome
Judgment entered for Resource Piling against Geocon on assessment of damages: awards for value of work, set-offs applied resulting in net sums due; additional awards for crane rental, standby charges and loss of profits; interest and costs awarded.
Legal Topics
Measure of Damages, Breach of Subcontract, Variation and Omission of Works, Delay and Standby Costs, Loss of Profits, Re Measurement Vs Design Quantities, Set Off/contra Charges, Repudiation
Source Language
english
Contract Construction Law Damages Measure of Damages Breach of Subcontract Variation and Omission of Works Delay and Standby Costs Loss of Profits +3 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Party arguments 2 Amounts and remedies 9
Sign in to unlock

Parties

Resource Piling Pte Ltd

Plaintiff

Geocon Piling & Engineering Pte Ltd

Defendant

Multi-Con Systems Pte Ltd

Defendant / Related Party

Procedural Posture

Civil: Contract (construction/subcontract) / Assessment of Damages After Liability Determined at Trial

  1. 1 Whether payment for piling works payable on actual length of piles installed or on design/drawing lengths
  2. 2 Whether Geocon breached the subcontract by failing to ensure crane-use term was incorporated into the main contract
  3. 3 Whether the parties agreed to omit/varied works at ECP Car Park A

Ratio Decidendi

The letter of award incorporated Resource's tender conditions and expressly required re-measurement by actual quantities, so payment was to be on actual pile lengths; Geocon breached by failing to secure the crane-use protection and by not ensuring unobstructed site access, causing delay and additional crane rental costs; those breaches amounted to repudiation when Geocon withheld payments, entitling Resource to recover crane rental, quantified standby charges and lost profits based on its historical profit margin; the ECP Car Park A works were omitted by agreement.

Court Disposition

Judgment entered for Resource Piling against Geocon on assessment of damages: awards for value of work, set-offs applied resulting in net sums due; additional awards for crane rental, standby charges and loss of profits; interest and costs awarded.

Orders

  • Geocon to pay Resource the net amount of $2,593,789.45 for value of work done after set-offs
  • Geocon to pay Resource $77,821.84 for crane rental