Download PDF

South Africa Judgment

Eastern Cape High Court, Grahamstown

Afri-Coast Engineers SA (Pty) Ltd v Amatola Water Board (546/18) [2018] ZAECGHC 31 (8 May 2018)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the respondent's defences, though legal in nature, were not far-fetched or bare denials intended solely to delay the applicant's remedy. The dispute resolution clause in the contract creates an obligation for both parties to attempt negotiation and mediation before approaching the court. The issue of confirming the availability of funds for services rendered beyond the contract period was not clearly allocated to either party, but the court held that the respondent, as custodian of its own budget, bore that responsibility. The requirement to give notice under the Institution of Legal Proceedings Against Certain Organs of State Act was found inapplicable, as the claim was not for damages. The court granted condonation for the late filing of the opposing affidavit, finding no prejudice to the applicant. Ultimately, the court determined that the respondent had raised a bona fide defence that should be properly ventilated at trial, and summary judgment was refused.

Court disposition

Summary judgment refused; defendant granted leave to defend; costs reserved for trial.

Orders

  • Summary judgment is refused.
  • The defendant is granted leave to defend the action.
  • Costs to be costs in the cause.

02

Material facts

Parties

Afri-Coast Engineers SA (Pty) Ltd

Applicant Counsel: Adv Boswell

Amatola Water Board

Respondent Counsel: Adv Stretch

Amounts and remedies

  • Claimed Amount: ZAR 2,297,907.76
  • Contract Value: ZAR 9,025,049.29

03

Procedural history

  1. Posture

    Summary Judgment Application / Application for Summary Judgment Following Notice to Defend; Opposed and Heard

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant contends that it rendered professional engineering services to the respondent under a written contract, performed its obligations, and was paid until July 2017. It claims R2,297,907.76 for unpaid services rendered beyond the initial 36-month contract period, plus interest and costs. The applicant argues that the respondent's notice to defend is solely for delay and that no bona fide defence exists. It further submits that the dispute resolution clause does not bar the present proceedings and that notice under the Institution of Legal Proceedings Against Certain Organs of State Act is not required as the claim is not for damages.
Respondent
The respondent raises three defences: (1) After expiry of the 36-month contract, the applicant was obliged to confirm the availability of further funds before rendering additional services, per clause 8.7; (2) The contract requires disputes to be resolved first by negotiation and mediation before litigation, per clauses 12.1 and 12.2; (3) The applicant was required to give notice to the Minister of Water and Sanitation under the Institution of Legal Proceedings Against Certain Organs of State Act before instituting proceedings. The respondent also seeks condonation for late filing of its opposing affidavit, citing the CEO's recent appointment and need to brief the Board.

05

Court’s reasoning

  1. 01

    Maharaj v Barclays National Bank Limited 1976 (1) SA 418 (A)

    Summary judgment may only be granted if the defendant does not disclose a bona fide defence and the plaintiff's claim is unimpeachable.

  2. 02

    Oos Rande Bantoesakke Administrasie Raad v Santam Versekeringsmaatskappy Bpk en andere 1978 (1) SA 164 (W); Slabert v Volkskas Bpk 1985 (1) SA 141 (T)

    A defendant opposing summary judgment must disclose the nature and material facts of its defence with sufficient particularity to enable the court to decide if it is bona fide.

  3. 03

    Arend & another v Astra Furnishers (Pty) Ltd 1974 (1) SA 298 (C)

    Courts are reluctant to grant summary judgment unless the plaintiff's claim is unanswerable and there is no doubt about its validity.

  4. 04

    Standard Professional Services Contract, Clause 12.1 and 12.2

    Contractual dispute resolution clauses requiring negotiation and mediation must be exhausted before litigation is initiated.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the respondent's defences, though legal in nature, were not far-fetched or bare denials intended solely to delay the applicant's remedy. The dispute resolution clause in the contract creates an obligation for both parties to attempt negotiation and mediation before approaching the court. The issue of confirming the availability of funds for services rendered beyond the contract period was not clearly allocated to either party, but the court held that the respondent, as custodian of its own budget, bore that responsibility. The requirement to give notice under the Institution of Legal Proceedings Against Certain Organs of State Act was found inapplicable, as the claim was not for damages. The court granted condonation for the late filing of the opposing affidavit, finding no prejudice to the applicant. Ultimately, the court determined that the respondent had raised a bona fide defence that should be properly ventilated at trial, and summary judgment was refused.

Obiter and limits

  • The defendant is not obliged to disclose all its defences in the opposing affidavit; the court may infer intended defences from the affidavit's content.
  • The usual costs order where summary judgment is refused is to reserve costs for determination by the trial court in the main action.
  • The discretion to grant or refuse summary judgment rests with the court, even if the requirements for resisting summary judgment have not been strictly met.

Court disposition

Summary judgment refused; defendant granted leave to defend; costs reserved for trial.

  • Summary judgment is refused.
  • The defendant is granted leave to defend the action.
  • Costs to be costs in the cause.

Source and reliance status

Eastern Cape High Court, Grahamstown

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Eastern Cape High Court, Grahamstown

Judgment

[2018] ZAECGHC 31

IN

THE HIGH COURT OF SOUTH AFRICA

{EASTERN CAPEDIVISION, GRAHAMSTOWN}

{EASTERN

CAPE

DIVISION,

GRAHAMSTOWN

Case No.546/18

Case No.

In the matter between:

AFRI-COAST ENGINEERS SA (PTY) LTDPlaintiff /Applicant

FRI-COAST ENGINEERS SA (PTY) LTD

Plaintiff /

Applicant

THE

AMATOLA WATER

BOARD

Defendant/Respondent

THE

A

MATOLA WATER

BOARD

Defendant/

Respondent

JUDGMENT

TONI

AJ

ONI AJ

[1] In this matter the plaintiff / applicant, a limited liability company, seeks summary judgment against the defendant/respondent for payment of a sum of R2 297 907.76, interest on the aforesaid sum at the prescribed legal rate of 10.5% per annum, calculated from the date of demand to the date of payment and costs.

[2] The application is a sequel to summons sued out by the plaintiff / applicant against the defendant / respondent on 23 February 2018 in terms whereof the prays for payment of the aforesaid sum, interest and costs. For the sake of simplicity and convenience, I will refer to the parties in this Judgment as they are referred to in the summons.

[3] The application is premised on Rule 32 (1) of the Rules of court which provides that:

“32 (1) Where the Defendant has delivered notice of intention to defend, the plaintiff may apply to the court for summary judgment on each of such claims in summons as is only -

32 (1) Where the Defendant has delivered notice of intention to defend, the plaintiff may apply to the court for summary judgment on each of such claims in summons as is only -

(a)on a liquid document;

on a liquid document;

(b)for liquidated amount in money;

for liquidated amount in money;

(c)for delivery of specified movable property;

for delivery of specified movable property;

(d)for ejectment; together with any claim for interest and costs”.

for ejectment; together with any claim for interest and costs”.

[4] In support of the summary judgment application is an affidavit deposed to by one Kevin T. Mcrae, “Mcrae”, ostensibly a director of the plaintiff. In the said affidavit, Mcrae verifies the plaintiff’s cause of action and confirms the

defendant’s indebtedness to the plaintiff before stating that in his opinion the defendant does not have abona fidedefence to the plaintiff’s claim and that the notice to defend has been filed solely for the purpose of delay.

[4] In support of the summary judgment application is an affidavit deposed to by one Kevin T. Mcrae, “Mcrae”, ostensibly a director of the plaintiff. In the said affidavit, Mcrae verifies the plaintiff’s cause of action and confirms the

defendant’s indebtedness to the plaintiff before stating that in his opinion the defendant does not have a

bona fide

defence to the plaintiff’s claim and that the notice to defend has been filed solely for the purpose of delay.

[5] The action is defended by the defendant and upon filing a notice of intention to defend on 13 March 2018, the plaintiff lodged the application for summary judgment on the grounds that the defendant does not have abona fidedefence to its claim and that the defendant has filed the notice to defend for the purpose of delay.

[5] The action is defended by the defendant and upon filing a notice of intention to defend on 13 March 2018, the plaintiff lodged the application for summary judgment on the grounds that the defendant does not have a

defence to its claim and that the defendant has filed the notice to defend for the purpose of delay

[6] The application is opposed by the defendant in support whereof it filed a notice to oppose on 25 April 2018. It is not so clear from the said notice when was it served on the plaintiff. What is apparent on the ultimate page thereof is that it was served at 12h25.

[7] The application was initially set to be heard on 17 April 2018 but was postponed to 24 April 2018 and the defendant was ordered to pay the costs occasioned by the postponement. On 24 April 2018 it was postponedsine dieand once again the defendant was ordered to pay the wasted costs.

[7] The application was initially set to be heard on 17 April 2018 but was postponed to 24 April 2018 and the defendant was ordered to pay the costs occasioned by the postponement. On 24 April 2018 it was postponed

sine die

and once again the defendant was ordered to pay the wasted costs.

[8] On 23 April 2018, a day before the date to which the application was postponed, the defendant filed its opposing affidavit which is deposed to by one Vuyo Zitumane, “Zitumane”, who is ostensibly the defendant’s Chief Executive Officer. In the said affidavit Zitumane sets out what is referred to therein as “Issues in Dispute” and in which the defendant’s

opposition to summary judgment is ostensibly premised. Zitumane further seeks condonation for the late filing of the defendant’s

opposing affidavit.

[9] I am required to determine whether, on the facts alleged by the plaintiff in its particulars of claim, I should grant summary

judgment or whether the defendant’s opposing affidavit discloses such abona fidedefence that I should refuse summary judgment. My first task is to deal with the application for condonation. I will deal with the defendant’s opposition to summary judgment later in this Judgment.

[9] I am required to determine whether, on the facts alleged by the plaintiff in its particulars of claim, I should grant summary

judgment or whether the defendant’s opposing affidavit discloses such a

defence that I should refuse summary judgment. My first task is to deal with the application for condonation. I will deal with the defendant’s opposition to summary judgment later in this Judgment.

[10] The condonation application stems from the defendant’s failure to file its affidavit opposing summary on time. Rule 32 (3) provides a defendant which wishes to oppose summary judgment with steps to follow, namely; (a) it must provide to the plaintiff security to the satisfaction of the Registrar, for any judgment including costs which may be given[1]or (b) it may, upon hearing of an application for summary judgment, satisfy the court by affidavit delivered before noon on a day but one before the court day (which affidavit may by leave of court be supplemented by oral evidence) that he has abona fidedefence to the claim on which summary judgment is sought or has abona fidecounterclaim against the plaintiff[2].

[10] The condonation application stems from the defendant’s failure to file its affidavit opposing summary on time. Rule 32 (3) provides a defendant which wishes to oppose summary judgment with steps to follow, namely; (a) it must provide to the plaintiff security to the satisfaction of the Registrar, for any judgment including costs which may be given

or (b) it may, upon hearing of an application for summary judgment, satisfy the court by affidavit delivered before noon on a day but one before the court day (which affidavit may by leave of court be supplemented by oral evidence) that he has a

defence to the claim on which summary judgment is sought or has a

counterclaim against the plaintiff

[11] The reasons proffered by Zitumane are embedded in paragraph 7 of the defendant’s opposing affidavit and these include,inter alia, that she is new in the office, having been appointed only on 9 April 2018, and thus she needed to familiarise herself with the issues involved in the application and brief the defendant’s Board. On the reasons advanced by Zitumane I am satisfied that the defendant was not in willful default and I granted condonation. No prejudice would be suffered by the plaintiff if condonation is granted as the matter was postponed on two occasions with the defendant having been mulcted with an appropriate order for the costs. In any event the application was not opposed by the plaintiff and the parties agreed that the summary judgment application should proceed.

[11] The reasons proffered by Zitumane are embedded in paragraph 7 of the defendant’s opposing affidavit and these include,

inter alia

, that she is new in the office, having been appointed only on 9 April 2018, and thus she needed to familiarise herself with the issues involved in the application and brief the defendant’s Board. On the reasons advanced by Zitumane I am satisfied that the defendant was not in willful default and I granted condonation. No prejudice would be suffered by the plaintiff if condonation is granted as the matter was postponed on two occasions with the defendant having been mulcted with an appropriate order for the costs. In any event the application was not opposed by the plaintiff and the parties agreed that the summary judgment application should proceed.

[12] The plaintiff’s claim against the defendant is based on contract for the provision of professional consulting engineering

services for one of the defendant’s projects, known as “the Upgrade of Binfield Water Supply Scheme: AW 2013/14/02”,

concluded on 22 July 2014[3]. The plaintiff was appointed by means of a letter from the Supply Chain Manager of the defendant dated 22 January 2014, annexed as “A” to the plaintiff’s particulars of claim. The value of the contract is R9 025 049.29.

[12] The plaintiff’s claim against the defendant is based on contract for the provision of professional consulting engineering

services for one of the defendant’s projects, known as “the Upgrade of Binfield Water Supply Scheme: AW 2013/14/02”,

concluded on 22 July 2014

. The plaintiff was appointed by means of a letter from the Supply Chain Manager of the defendant dated 22 January 2014, annexed as “A” to the plaintiff’s particulars of claim. The value of the contract is R9 025 049.29.

[13] The material terms of the agreement between the plaintiff and the defendant are in writing and are contained in a “Standard

Professional Services Contract”, annexed as “E” to the plaintiff’s particulars of claim. It was agreed as between the parties that the Standard Professional Services Contract (September 2005) (second edition of CIDB document 1014) would be applicable to the contract, subject to the variations, amendments and additions set out in annexure “D” to the particulars of claim.

[14] It is common cause, it having been specifically pleaded by the plaintiff in its particulars of claim and it having been raised in defence by the defendant in its opposing affidavit, that the contract was of a limited duration of 36 months from the date of appointment and will extend “until the completion of all instructions that were issued during this period, subject to the availability of the funding for the

Project”[4].

[14] It is common cause, it having been specifically pleaded by the plaintiff in its particulars of claim and it having been raised in defence by the defendant in its opposing affidavit, that the contract was of a limited duration of 36 months from the date of appointment and will extend “

until the completion of all instructions that were issued during this period, subject to the availability of the funding for the

Project”

[15] It is further common cause that the Standard Professional Services contract contains a dispute resolution Clause that is binding on both parties. The dispute resolution mechanism is provided for in Clause 12.1 of the contract as follows:

“12.1Settlement

Settlement

12.1.1 The Parties shall negotiate in good faith with a view to settling any dispute or claim arising out of or relating to the Contract and may not initiate any further proceedings until either Party has, by written notice to the other, declared that such negotiations have failed;

12.1.2 Any dispute or claim arising out of or relating to Contract which cannot be settled between the Partiesshall[5]in the first instance be referred by the Parties to either mediation or adjudication as provided for in the Contract Data”.

12.1.2 Any dispute or claim arising out of or relating to Contract which cannot be settled between the Parties

in the first instance be referred by the Parties to either mediation or adjudication as provided for in the Contract Data”

[16]Clauses 12.2, 12.3 and 12.4 set out broadly the process to be followed before referring the dispute to either mediation, adjudication and arbitration. It is not necessary for the purpose of this Judgment to dwell much on the above processes as such intricate detail may only serve to cloud issues.

Clauses 12.2, 12.3 and 12.4 set out broadly the process to be followed before referring the dispute to either mediation, adjudication and arbitration. It is not necessary for the purpose of this Judgment to dwell much on the above processes as such intricate detail may only serve to cloud issues.

[17]To make a determination whether to grant or refuse summary judgment, I will confine myself to the facts averred by the plaintiff as against the defence raised by the defendant, even though open to some doubt. The plaintiff’s claim is crystallized in paragraph 16 of its particulars of claim annexed to the summons. In said paragraph the plaintiff avers that it “has performed in terms of its obligations to the defendant in terms of the contract during the envisaged 36 months and thereafter”. In paragraph 17 the plaintiff further avers that “the defendant, until July 2017, paid the plaintiff for the services it rendered, in respect of the project, in terms of the contract”.

To make a determination whether to grant or refuse summary judgment, I will confine myself to the facts averred by the plaintiff as against the defence raised by the defendant, even though open to some doubt

. The plaintiff’s claim is crystallized in paragraph 16 of its particulars of claim annexed to the summons. In said paragraph the plaintiff avers that it “

has performed in terms of its obligations to the defendant in terms of the contract during the envisaged 36 months and thereafter

”. In paragraph 17 the plaintiff further avers that “

the defendant, until July 2017, paid the plaintiff for the services it rendered, in respect of the project, in terms of the contract”

[18] It is clear in mind, therefore, that the period for which the plaintiff has not been paid is for services it has rendered beyond

the period of 36 months envisaged by the contract. This has been conceded to as much by both Counsel during their argument.

What falls to be determined, therefore, is whether the defence raised by the defendant in its opposing affidavit isbona fide.The defendant’s defence is threefold, namely;

bona fide.

18.1 Upon expiry of the 36 months period envisaged by the contract, the plaintiff was obliged to approach the defendant and confirm the availability of further funds before rendering further services. This, according to the defendant is in keeping with Clause 8.7 of the contract. As the plaintiff has failed to confirm the availability of further funds at the end of the contract and it is thus not entitled to claim any further services allegedly rendered in terms of the contract.

18.2 The defendant further relied on Clause 12.1 and 12.2 of the contract which makes a provision for a dispute resolution mechanism in the event of dispute arising between the parties. The defendant’s contention is that the plaintiff was obliged under the said clause to resort to mediation before approaching the court.

18.3 The defendant also sought to rely on section 3 (1) (b) of the Institution of Legal Proceedings Against Certain Organs of the State Act,2002, Act 40of 2002, “the Act”, in that before instituting the said proceedings, the plaintiff was obliged to first give notice of the intended legal action to the Minister of Water and Sanitation.

2002, Act 40

[19] I do not agree with the defendant in respect of its last line of defence. During argument Counsel for the defendant conceded as much, and correctly in my view, that such notice was not necessary in the circumstances and that the defendant would no longer pursue its defence on this leg. The plaintiff’s claim is not a debt as defined in the Act as debt is confined to a claim for damages[6].

[19] I do not agree with the defendant in respect of its last line of defence. During argument Counsel for the defendant conceded as much, and correctly in my view, that such notice was not necessary in the circumstances and that the defendant would no longer pursue its defence on this leg. The plaintiff’s claim is not a debt as defined in the Act as debt is confined to a claim for damages

[20] The court is saddled with a responsibility to examined the above two defences and determine whether within the meaning and contemplation of Rule 32 (3) (b) they arebona fideenough to avoid summary judgment.It is trite that for the Defendant to resist summary judgment he may satisfy the court on affidavit that he has abona fidedefence to the Plaintiff’s claim. The affidavit must disclose the nature of defence and the material facts relied upon[7].

[20] The court is saddled with a responsibility to examined the above two defences and determine whether within the meaning and contemplation of Rule 32 (3) (b) they are

enough to avoid summary judgment.

It is trite that for the Defendant to resist summary judgment he may satisfy the court on affidavit that he has a

defence to the Plaintiff’s claim. The affidavit must disclose the nature of defence and the material facts relied upon

[21]The Defendant need not deal exhaustively with the facts andevidence relied upon to substantiate them but he must at least disclose his defence and the material facts upon which it is based with sufficient particularity and completeness to enable the court to decide whether the affidavit discloses abona fidedefence or not.The discretion to grant or refuse summary judgment, even if the requirements resisting summary judgment have not been met, restswith the court[8].

The Defendant need not deal exhaustively with the facts and

vidence relied upon to substantiate them but he must at least disclose his defence and the material facts upon which it is based with sufficient particularity and completeness to enable the court to decide whether the affidavit discloses a

defence or not.

The discretion to grant or refuse summary judgment, even if the requirements resisting summary judgment have not been met, rest

with the court

[22] In Maharaj v Barclays National Bank Limited[9], the words of Corbett JA are resonating. He said:

[22] In Maharaj v Barclays National Bank Limited

, the words of Corbett JA are resonating. He said:

“The grant of the remedy is based on the supposition that the plaintiff’s claim is unimpeachable and that the defendant’s defence is bogus and bad in law”[10].

The test is whether on the set of facts before it, the court is able to conclude that the defence raised by the defendant is bogus or is bad in law.

[23] Courts are extremely loath to grant summary judgment unless satisfied that the Plaintiff has an unanswerable case.It is only when there is no doubt about the Plaintiff’s claim that the court can revisit its leniency and grant summary judgment[11].

[23] C

ourts are extremely loath to grant summary judgment unless satisfied that the Plaintiff has an unanswerable case.

It is only when there is no doubt about the Plaintiff’s claim that the court can revisit its leniency and grant summary judgment

[24] In this case the defendant has raised two defences, referred to in its opposing affidavit as “issues in dispute”, which if advanced at trial have the potential to dislodge the plaintiff in its claim. I am not minded by the manner in which these defences are referred to in the opposing affidavit or with the fact that the defendant may not have disclosed all its defences. The defendant is not obliged to disclose all its defences in the opposing affidavit. Similarly a court is also not necessarily bound to the manner in which the defendant has presented his case and is entitled to ascertain from the content of the affidavit itself and draw an inference[12]of what the defendant actually intended to say.

[24] In this case the defendant has raised two defences, referred to in its opposing affidavit as “

issues in dispute

”, which if advanced at trial have the potential to dislodge the plaintiff in its claim. I am not minded by the manner in which these defences are referred to in the opposing affidavit or with the fact that the defendant may not have disclosed all its defences. The defendant is not obliged to disclose all its defences in the opposing affidavit. Similarly a court is also not necessarily bound to the manner in which the defendant has presented his case and is entitled to ascertain from the content of the affidavit itself and draw an inference

of what the defendant actually intended to say.

[25] Although the two defences raised by the plaintiff are of a legal nature, these cannot be said to be far-fetched, bogus or bare denials designed only to delay the plaintiff from obtained a quick remedy. Both defences are founded in the contract the terms whereof are sought to be enforced by the plaintiff. It seems to me that the appropriate forum to have these defences properly ventilated is the trial court itself.

[26] Clause 8.7 of the contract creates a condition upon which the contract between that parties may be extended and makes the availability of funds asine qua nonto the extension of the contract. It is not clear in the contract which of the parties has an obligation to confirm the availability of funds. However, it being a repository of a discretion whether to extend the contract or not, it would be safe to assume that the defendant bears that responsibility. The defendant is the custodian of its own budget and funds to be allocated to the project. In this regard I do not agree with the defendant’s contention that the plaintiff had an obligation to confirm the availability of funds before proceeding with the project beyond its term of 36 months.

[26] Clause 8.7 of the contract creates a condition upon which the contract between that parties may be extended and makes the availability of funds a

sine qua non

to the extension of the contract. It is not clear in the contract which of the parties has an obligation to confirm the availability of funds. However, it being a repository of a discretion whether to extend the contract or not, it would be safe to assume that the defendant bears that responsibility. The defendant is the custodian of its own budget and funds to be allocated to the project. In this regard I do not agree with the defendant’s contention that the plaintiff had an obligation to confirm the availability of funds before proceeding with the project beyond its term of 36 months.

[27] The above having been said it does not, however, shift the focus on whether the defendant has abona fidedefence to the plaintiff’s claim.

[27] The above having been said it does not, however, shift the focus on whether the defendant has a

defence to the plaintiff’s claim.

[28] Clauses 12.1 and 12.2 to the contract further creates an obligation on both the plaintiff and the defendant to first exhaust internal remedies provided for in the contract to first attempt to resolve any dispute arising out of the agreement, through negotiations and failing negotiations through mediation and

failing mediation through adjudication up to a stage of arbitration in the event that the above processes have failed. Clause 12.1 specifically provides that:

12.1.1 The parties shall negotiate in good faith with a view to settling any dispute or claim arising out of or relating to the Contract and may not initiate any further proceedings until either Party has, by written notice to the other, declared that such negotiations have failed;

[28] Clause 12.2 sets out in succinct detail the process to be followed when referring the matter to mediation, the process to be followed in selecting the mediator, the costs of the mediator, the process to be followed by the mediator in attempting to resolve the dispute, powers of the mediator to end the mediation process as well as referral of the dispute to arbitration in the event of failure of the mediation process. Clause 12.3 and 12.4 deals with the adjudication and arbitration processes.

[29] In the light of the above it would seem to me that the most appropriate forum to determine whether or not the defendant would be successful with its defence is the trial court. I am, therefore, convinced that the defendant has raised abona fidedefence to the plaintiff’s claim. The summary judgment application should fail.

[29] In the light of the above it would seem to me that the most appropriate forum to determine whether or not the defendant would be successful with its defence is the trial court. I am, therefore, convinced that the defendant has raised a

defence to the plaintiff’s claim. The summary judgment application should fail.

The Costs

[30] With regard to the issue of the costs, the usual costs order where summary judgment is refused is to reserve the costs for determination by the trial court and to make such order for costs to be in the main action. I see no reason to deviate from such position.

[31] In the result, I make the following order:

1.Summary Judgment is refused.

Summary Judgment is refused.

2. The defendant is granted leave to defend the action.

3. Costs to be costs in the cause.

_______

ACTING

JUDGE OF THE HIGH COURT

Counsel for the plaintiff

:

Adv Boswell

Instructed b y

:

Van Zyl’s Inc

c/o

NETTELTONS

GRAHAMSTOWN

Counsel for the defendant

:

Adv Stretch

Instructed b y

:

Ntsiki Pakade Attorneys

c/o WHEELDON RUSHMERE & CLOETE ATTORNEYS

HEARD ON

: 02 MAY 2018

DELIVERED ON

: 08 MAY 2018

[1]Rule 32 (3) (a)

[2]Rule 32 (3) (b)

[3]Par. 4, plaintiff’s particulars of claim, par.; Record p.5

[4]2. Clause 8.7

[5]3. My emphasis

[6]See The unreported Judgment of Vna Zyl AJA in Vhembe District Municipality v Stewards & Lloyds Booysen (Pty) Ltd and Ano

(397/2013)[2014] ZASCA 93(26 jUNE 2014); Also Nicor IT cONSULTING (Pty) Ltd v North West Housing Cooporation2010 (3) SA 90(NWM); Director General, Department of Public Works V kOVAC investments2010 (6) SA 646(GNP); Thabani Zulu & Co (Pty) Ltd v Minister of Water Affairs 7 ano 2012 (4) SA 91 (KZD)

[2014] ZASCA 93

2010 (3) SA 90

2010 (6) SA 646

[7]Oos Rande Bantoesakke Adminstrasie Raad v Santam Versekeringsmaatskappy Bpk en andere1978 (1) SA 164(W); Slabert v Volkskas Bpk 1985 (1) SA 141 (T)

Oos Rande Bantoesakke Adminstrasie Raad v Santam Versekeringsmaatskappy Bpk en andere1978 (1) SA 164(W); Slabert v Volkskas Bpk 1985 (1) SA 141 (T)

1978 (1) SA 164

[8]Mahomed Essop (Pty) Ltd v Sekhukhulu and sons1967 (3) SA 728D.First National Bank of South West AfricaLtd v Graap 1990 NR 9 (HC)

Mahomed Essop (Pty) Ltd v Sekhukhulu and sons1967 (3) SA 728D.First National Bank of South West AfricaLtd v Graap 1990 NR 9 (HC)

1967 (3) SA 728

[9]1976 (1) SA 418(A)

1976 (1) SA 418

[10]1976 (1) SA 418(A) at 423G

[11]Per Cobertt J in Arend & another v Astra Furnishers (Pty) Ltd1974 (1) SA 298(C) at 304F – 305

Per Cobertt J in Arend & another v Astra Furnishers (Pty) Ltd1974 (1) SA 298(C) at 304F – 305

1974 (1) SA 298

[12]Fashion Centre v Jasat1960 (3) SA 221(N) at 222G

1960 (3) SA 221

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Maharaj v Barclays National Bank Limited 1976 (1) SA 418 (A)

Case cited

Oos Rande Bantoesakke Administrasie Raad v Santam Versekeringsmaatskappy Bpk en andere 1978 (1) SA 164 (W)

Case cited

Slabert v Volkskas Bpk 1985 (1) SA 141 (T)

Case cited

Arend & another v Astra Furnishers (Pty) Ltd 1974 (1) SA 298 (C)

Case cited

Fashion Centre v Jasat 1960 (3) SA 221 (N)

Case cited

Mahomed Essop (Pty) Ltd v Sekhukhulu and sons 1967 (3) SA 728 (D)

Case cited

First National Bank of South West Africa Ltd v Graap 1990 NR 9 (HC)

Case cited

Vhembe District Municipality v Stewards & Lloyds Booysen (Pty) Ltd and Another (397/2013) [2014] ZASCA 93 (26 June 2014)

Case cited

Nicor IT Consulting (Pty) Ltd v North West Housing Corporation 2010 (3) SA 90 (NWM)

Case cited

Director General, Department of Public Works v Kovac Investments 2010 (6) SA 646 (GNP)

Case cited

Thabani Zulu & Co (Pty) Ltd v Minister of Water Affairs and Another 2012 (4) SA 91 (KZD)

Case cited

Institution of Legal Proceedings Against Certain Organs of State Act, 2002 (Act 40 of 2002)

Legislation

Legislation referenced in the available case record.

Standard Professional Services Contract (CIDB document 1014)

Legislation

Legislation referenced in the available case record.

Uniform Rules of Court, Rule 32

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.